| Sr. | New Work Type | Total works | Ongoing | Completed | Closed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|---|---|---|
| 1 | Rural Housing | 417 | 76 | 288 | 0 | 83.27 | 65.81 | 79% |
| 2 | Construction of Well | 33 | 5 | 16 | 2 | 49.60 | 24.06 | 49% |
| 3 | Construction of Trench | 27 | 0 | 25 | 1 | 34.22 | 24.49 | 72% |
| 4 | Construction of Check Dam/Stop Dam | 18 | 6 | 9 | 0 | 25.49 | 14.62 | 57% |
| 5 | Plantation | 17 | 2 | 7 | 7 | 41.26 | 8.21 | 20% |
| 6 | Constr of Cement Concrete Roads | 16 | 0 | 7 | 5 | 31.93 | 11.67 | 37% |
| 7 | Land Development | 14 | 0 | 1 | 0 | 6.93 | 1.32 | 19% |
| 8 | Construction of Road and Culvert | 14 | 0 | 11 | 2 | 49.14 | 26.67 | 54% |
| 9 | Underground Dyke for Ground Water Recharge | 11 | 0 | 9 | 0 | 37.14 | 17.03 | 46% |
| 10 | Construction of Toilets | 11 | 0 | 0 | 0 | 3.64 | 0.00 | 0% |
| 11 | Farm Pond | 10 | 1 | 8 | 1 | 12.39 | 7.02 | 57% |
| 12 | Construction of NADEP/Vermi Compost Pit | 8 | 0 | 2 | 4 | 1.61 | 0.15 | 9% |
| 13 | Well Recharge | 4 | 0 | 1 | 0 | 2.81 | 1.54 | 55% |
| 14 | Construction of Bund | 4 | 0 | 0 | 1 | 0.75 | 0.00 | 0% |
| 15 | Works for Flood Control and Protection | 3 | 0 | 0 | 0 | 9.91 | 4.86 | 49% |
| 16 | Construction of Tank | 2 | 1 | 1 | 0 | 2.18 | 0.93 | 43% |
| 17 | Constr of Aganwadi | 2 | 0 | 1 | 0 | 4.25 | 2.28 | 54% |
| 18 | Construction of Water Drain/Diversion Channel/Drainage/Field Channel | 2 | 0 | 2 | 0 | 2.02 | 0.45 | 22% |
| 19 | Solid and Liquid Waste Management | 2 | 0 | 0 | 2 | 0.41 | 0.00 | 0% |
| 20 | Construction of Play field | 1 | 0 | 0 | 0 | 1.53 | 0.00 | 0% |
| 21 | Construction of Percolation Tank | 1 | 0 | 0 | 0 | 1.88 | 0.00 | 0% |
| 22 | Cattle Shed | 1 | 0 | 0 | 1 | 1.26 | 0.00 | 0% |
| 23 | Constr of GP Bhawan | 1 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| 24 | Community Sanitary Complex | 1 | 0 | 1 | 0 | 0.43 | 0.40 | 94% |
| 25 | Boulder Check/Gully Plug | 1 | 0 | 0 | 1 | 2.74 | 0.00 | 0% |
| Total | 621 | 91 | 389 | 28 | 406.79 | 211.50 |