| Sr. | New Work Type | Total works | Ongoing | Completed | Closed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|---|---|---|
| 1 | Rural Housing | 149 | 17 | 93 | 1 | 0.29 | 0.22 | 77% |
| 2 | Construction of NADEP/Vermi Compost Pit | 36 | 0 | 16 | 1 | 0.01 | 0.00 | 51% |
| 3 | Construction of Check Dam/Stop Dam | 33 | 0 | 23 | 3 | 1.31 | 1.10 | 84% |
| 4 | Construction of Toilets | 27 | 0 | 22 | 0 | 0.02 | 0.02 | 87% |
| 5 | Plantation | 23 | 0 | 13 | 9 | 0.54 | 0.30 | 56% |
| 6 | Construction of Percolation Tank | 22 | 0 | 14 | 7 | 0.50 | 0.35 | 71% |
| 7 | Construction of Tank | 18 | 2 | 9 | 1 | 0.33 | 0.26 | 78% |
| 8 | Construction of Well | 16 | 5 | 2 | 0 | 0.36 | 0.18 | 51% |
| 9 | Constr of Cement Concrete Roads | 16 | 0 | 13 | 1 | 0.42 | 0.35 | 84% |
| 10 | Construction of Road and Culvert | 13 | 0 | 7 | 0 | 0.64 | 0.29 | 46% |
| 11 | Farm Pond | 11 | 0 | 10 | 0 | 0.20 | 0.18 | 87% |
| 12 | Land Development | 5 | 0 | 1 | 0 | 0.04 | 0.00 | 0% |
| 13 | Constr of Aganwadi | 4 | 0 | 2 | 1 | 0.04 | 0.03 | 92% |
| 14 | Community Sanitary Complex | 3 | 0 | 2 | 1 | 0.01 | 0.01 | 97% |
| 15 | Construction of Recharge Pits | 2 | 0 | 0 | 0 | 0.01 | 0.00 | 0% |
| 16 | Construction of Play field | 2 | 0 | 2 | 0 | 0.03 | 0.01 | 41% |
| 17 | Repair & maint of Percolation Tank | 1 | 0 | 1 | 0 | 0.03 | 0.03 | 78% |
| 18 | Construction of Crematorium | 1 | 0 | 1 | 0 | 0.05 | 0.02 | 43% |
| 19 | Well Recharge | 1 | 0 | 1 | 0 | 0.05 | 0.04 | 81% |
| Total | 383 | 24 | 232 | 25 | 4.87 | 3.41 |