| Sr. | New Work Type | Total works | Ongoing | Completed | Closed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|---|---|---|
| 1 | Rural Housing | 277 | 30 | 246 | 0 | 0.50 | 0.47 | 94% |
| 2 | Construction of Toilets | 68 | 1 | 46 | 1 | 0.06 | 0.04 | 68% |
| 3 | Construction of Road and Culvert | 22 | 1 | 10 | 0 | 1.57 | 0.29 | 19% |
| 4 | Plantation | 19 | 6 | 3 | 3 | 0.46 | 0.02 | 5% |
| 5 | Construction of NADEP/Vermi Compost Pit | 16 | 0 | 0 | 0 | 0.17 | 0.00 | 0% |
| 6 | Farm Pond | 16 | 0 | 8 | 0 | 0.30 | 0.23 | 75% |
| 7 | Constr of Cement Concrete Roads | 12 | 1 | 6 | 2 | 0.79 | 0.36 | 46% |
| 8 | Cattle Shed | 11 | 0 | 9 | 0 | 0.07 | 0.03 | 37% |
| 9 | Construction of Crematorium | 9 | 2 | 3 | 1 | 0.18 | 0.10 | 58% |
| 10 | Construction of Bund | 9 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| 11 | Construction of Check Dam/Stop Dam | 8 | 0 | 4 | 2 | 0.29 | 0.19 | 65% |
| 12 | Construction of Trench | 7 | 0 | 5 | 2 | 0.05 | 0.03 | 70% |
| 13 | Constr of Aganwadi | 4 | 0 | 2 | 0 | 0.07 | 0.03 | 51% |
| 14 | Construction of Play field | 4 | 0 | 0 | 0 | 0.09 | 0.00 | 0% |
| 15 | Solid and Liquid Waste Management | 2 | 1 | 0 | 0 | 0.01 | 0.00 | 74% |
| 16 | Community Sanitary Complex | 2 | 1 | 0 | 0 | 0.01 | 0.00 | 34% |
| 17 | Construction of Recharge Pits | 2 | 0 | 0 | 0 | 0.01 | 0.00 | 49% |
| 18 | Construction of Tank | 2 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| 19 | Construction of Well | 2 | 0 | 0 | 1 | 0.02 | 0.00 | 0% |
| 20 | Land Development | 2 | 0 | 0 | 0 | 0.02 | 0.00 | 0% |
| 21 | Repair & maint of Percolation Tank | 1 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| 22 | Repair & maint of Pond/ Tank | 1 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| 23 | Nursery Development | 1 | 1 | 0 | 0 | 0.52 | 0.01 | 3% |
| 24 | Construction of Percolation Tank | 1 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| Total | 498 | 44 | 342 | 15 | 5.18 | 1.82 |