| Sr. | New Work Type | Total works | Ongoing | Completed | Closed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|---|---|---|
| 1 | Construction of Tank | 66 | 15 | 10 | 3 | 6.52 | 3.93 | 60% |
| 2 | Rural Housing | 36 | 0 | 34 | 0 | 0.06 | 0.05 | 91% |
| 3 | Construction of Road and Culvert | 21 | 0 | 12 | 3 | 1.72 | 1.51 | 88% |
| 4 | Repair & maint of Pond/ Tank | 21 | 0 | 15 | 3 | 1.87 | 1.78 | 95% |
| 5 | Plantation | 19 | 6 | 5 | 2 | 0.78 | 0.31 | 40% |
| 6 | Works for Flood Control and Protection | 16 | 0 | 13 | 0 | 1.56 | 1.30 | 84% |
| 7 | Construction of Bund | 14 | 10 | 2 | 0 | 2.02 | 0.85 | 42% |
| 8 | Construction of Trench | 13 | 0 | 8 | 0 | 0.43 | 0.29 | 69% |
| 9 | Construction of Check Dam/Stop Dam | 12 | 0 | 10 | 0 | 1.22 | 1.18 | 97% |
| 10 | Cattle Shed | 11 | 0 | 3 | 0 | 0.48 | 0.42 | 88% |
| 11 | Construction of Recharge Pits | 11 | 0 | 8 | 0 | 0.04 | 0.04 | 90% |
| 12 | Farm Pond | 11 | 0 | 11 | 0 | 0.03 | 0.03 | 98% |
| 13 | Constr of Cement Concrete Roads | 10 | 0 | 6 | 0 | 0.07 | 0.05 | 74% |
| 14 | Land Development | 6 | 0 | 6 | 0 | 0.07 | 0.06 | 92% |
| 15 | Construction of Water Drain/Diversion Channel/Drainage/Field Channel | 6 | 0 | 5 | 0 | 0.75 | 0.73 | 98% |
| 16 | Construction of Percolation Tank | 5 | 0 | 4 | 0 | 0.44 | 0.42 | 95% |
| 17 | Construction of NADEP/Vermi Compost Pit | 4 | 0 | 2 | 0 | 0.10 | 0.03 | 34% |
| 18 | Construction of Crematorium | 4 | 0 | 2 | 2 | 0.06 | 0.05 | 91% |
| 19 | Community Sanitary Complex | 3 | 0 | 1 | 0 | 0.01 | 0.01 | 95% |
| 20 | Repair & Maint of Community infrastructure | 3 | 0 | 1 | 1 | 0.00 | 0.00 | 14% |
| 21 | Construction of Play field | 2 | 0 | 2 | 0 | 0.06 | 0.05 | 75% |
| 22 | Construction of Toilets | 2 | 0 | 1 | 0 | 0.00 | 0.00 | 47% |
| 23 | Constr of GP Bhawan | 2 | 0 | 1 | 0 | 0.24 | 0.09 | 39% |
| 24 | Renovation of traditional water bodies | 2 | 0 | 2 | 0 | 0.01 | 0.01 | 94% |
| 25 | Well Recharge | 2 | 1 | 1 | 0 | 0.00 | 0.00 | 91% |
| 26 | Grass Land Development | 1 | 1 | 0 | 0 | 0.08 | 0.01 | 17% |
| 27 | Deepening / Desilting of Flood Channels | 1 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| 28 | Constr of Aganwadi | 1 | 0 | 1 | 0 | 0.03 | 0.02 | 81% |
| 29 | Construction of Embankment | 1 | 0 | 1 | 0 | 0.09 | 0.08 | 87% |
| 30 | Repair & Maint of Check Dam/Stop Dam | 1 | 0 | 1 | 0 | 0.09 | 0.09 | 100% |
| Total | 307 | 33 | 168 | 14 | 18.84 | 13.42 |