| Sr. | New Work Type | Total works | Ongoing | Completed | Closed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|---|---|---|
| 1 | Construction of Toilets | 77 | 0 | 44 | 0 | 3.34 | 1.55 | 46% |
| 2 | Cattle Shed | 58 | 0 | 12 | 0 | 15.88 | 6.42 | 40% |
| 3 | Constr of Cement Concrete Roads | 39 | 0 | 29 | 1 | 40.66 | 30.18 | 74% |
| 4 | Terracing | 37 | 0 | 29 | 0 | 8.92 | 7.78 | 87% |
| 5 | Construction of Check Dam/Stop Dam | 32 | 0 | 17 | 5 | 85.50 | 41.82 | 49% |
| 6 | Land Development | 27 | 0 | 2 | 0 | 28.00 | 10.79 | 39% |
| 7 | Construction of Bund | 21 | 0 | 10 | 3 | 46.22 | 22.32 | 48% |
| 8 | Construction of NADEP/Vermi Compost Pit | 21 | 0 | 10 | 11 | 1.42 | 1.01 | 71% |
| 9 | Farm Pond | 17 | 1 | 9 | 1 | 42.08 | 28.74 | 68% |
| 10 | Rural Housing | 16 | 2 | 2 | 3 | 3.27 | 0.92 | 28% |
| 11 | Works for Flood Control and Protection | 11 | 1 | 4 | 4 | 51.68 | 15.44 | 30% |
| 12 | Construction of Trench | 10 | 1 | 5 | 1 | 63.88 | 33.60 | 53% |
| 13 | Solid and Liquid Waste Management | 7 | 3 | 4 | 0 | 0.32 | 0.30 | 94% |
| 14 | Plantation | 6 | 0 | 2 | 2 | 19.87 | 0.27 | 1% |
| 15 | Construction of Road and Culvert | 5 | 0 | 5 | 0 | 20.07 | 17.31 | 86% |
| 16 | Construction of Crematorium | 5 | 0 | 1 | 2 | 4.90 | 2.45 | 50% |
| 17 | Constr of GP Bhawan | 5 | 2 | 2 | 0 | 57.30 | 50.61 | 88% |
| 18 | Community Sanitary Complex | 3 | 0 | 2 | 1 | 1.29 | 0.82 | 64% |
| 19 | Constr of Aganwadi | 3 | 0 | 3 | 0 | 6.90 | 7.32 | 106% |
| 20 | Construction of Play field | 2 | 0 | 1 | 1 | 3.20 | 3.16 | 99% |
| 21 | Repair & maint of Pond/ Tank | 1 | 0 | 1 | 0 | 9.80 | 5.48 | 56% |
| 22 | Constr of Compound wall | 1 | 0 | 0 | 0 | 0.70 | 0.00 | 0% |
| 23 | Construction of Spur | 1 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| 24 | Well Recharge | 1 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| 25 | Renovation of traditional water bodies | 1 | 0 | 0 | 0 | 1.00 | 0.00 | 0% |
| Total | 407 | 10 | 194 | 36 | 516.18 | 288.29 |