| Sr. | New Work Type | Total works | Ongoing | Completed | Closed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|---|---|---|
| 1 | Construction of Toilets | 67 | 0 | 56 | 0 | 4.42 | 3.97 | 90% |
| 2 | Constr of Cement Concrete Roads | 42 | 0 | 32 | 5 | 34.74 | 34.43 | 99% |
| 3 | Cattle Shed | 15 | 0 | 2 | 0 | 2.70 | 1.76 | 65% |
| 4 | Construction of Check Dam/Stop Dam | 12 | 3 | 7 | 1 | 50.74 | 21.86 | 43% |
| 5 | Works for Flood Control and Protection | 11 | 7 | 0 | 2 | 36.36 | 20.37 | 56% |
| 6 | Construction of Crematorium | 11 | 3 | 2 | 4 | 33.90 | 19.64 | 58% |
| 7 | Construction of Recharge Pits | 11 | 0 | 0 | 10 | 0.47 | 0.00 | 0% |
| 8 | Plantation | 9 | 2 | 1 | 4 | 18.77 | 3.04 | 16% |
| 9 | Rural Housing | 8 | 0 | 4 | 0 | 1.39 | 0.62 | 45% |
| 10 | Repair & maint of Pond/ Tank | 7 | 1 | 3 | 3 | 20.46 | 8.77 | 43% |
| 11 | Construction of Road and Culvert | 7 | 1 | 4 | 2 | 28.75 | 16.70 | 58% |
| 12 | Construction of NADEP/Vermi Compost Pit | 6 | 0 | 5 | 0 | 1.05 | 0.97 | 92% |
| 13 | Construction of Bund | 4 | 0 | 4 | 0 | 3.80 | 3.22 | 85% |
| 14 | Construction of Trench | 3 | 0 | 2 | 1 | 13.39 | 9.28 | 69% |
| 15 | Constr of Aganwadi | 2 | 0 | 2 | 0 | 5.10 | 5.04 | 99% |
| 16 | Construction of Play field | 2 | 1 | 1 | 0 | 15.60 | 6.19 | 40% |
| 17 | Community Sanitary Complex | 2 | 1 | 1 | 0 | 0.86 | 0.47 | 55% |
| 18 | Construction of Tank | 2 | 2 | 0 | 0 | 67.43 | 2.39 | 4% |
| 19 | Renovation of traditional water bodies | 2 | 0 | 1 | 0 | 1.98 | 0.83 | 42% |
| 20 | Culvert | 1 | 0 | 0 | 0 | 1.25 | 1.53 | 123% |
| 21 | Construction of Percolation Tank | 1 | 0 | 1 | 0 | 8.19 | 4.49 | 55% |
| 22 | Constr of GP Bhawan | 1 | 1 | 0 | 0 | 10.00 | 9.46 | 95% |
| 23 | Construction of building/workshed for SHG | 1 | 0 | 0 | 0 | 3.30 | 0.00 | 0% |
| 24 | Land Development | 1 | 0 | 1 | 0 | 5.00 | 3.71 | 74% |
| Total | 228 | 22 | 129 | 32 | 369.64 | 178.73 |