| Sr. | New Work Type | Total works | Ongoing | Completed | Closed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|---|---|---|
| 1 | Construction of Bund | 33 | 1 | 17 | 3 | 0.16 | 0.14 | 86% |
| 2 | Works for Flood Control and Protection | 28 | 7 | 0 | 21 | 0.53 | 0.04 | 7% |
| 3 | Construction of Water Drain/Diversion Channel/Drainage/Field Channel | 25 | 1 | 16 | 1 | 2.01 | 1.68 | 83% |
| 4 | Constr of Cement Concrete Roads | 23 | 0 | 13 | 2 | 0.16 | 0.11 | 65% |
| 5 | Construction of Check Dam/Stop Dam | 18 | 1 | 6 | 3 | 1.09 | 0.81 | 74% |
| 6 | Construction of NADEP/Vermi Compost Pit | 18 | 0 | 8 | 10 | 0.01 | 0.01 | 81% |
| 7 | Construction of Road and Culvert | 11 | 2 | 5 | 2 | 1.58 | 1.11 | 70% |
| 8 | Plantation | 11 | 4 | 3 | 2 | 0.26 | 0.01 | 5% |
| 9 | Farm Pond | 10 | 0 | 0 | 2 | 0.00 | 0.00 | 0% |
| 10 | Construction of Tank | 6 | 0 | 1 | 5 | 0.08 | 0.01 | 17% |
| 11 | Rural Housing | 6 | 0 | 6 | 0 | 0.01 | 0.01 | 78% |
| 12 | Cattle Shed | 5 | 0 | 3 | 1 | 0.01 | 0.00 | 53% |
| 13 | Land Development | 4 | 0 | 0 | 0 | 0.02 | 0.00 | 0% |
| 14 | Construction of Trench | 3 | 0 | 3 | 0 | 0.23 | 0.22 | 94% |
| 15 | Constr of GP Bhawan | 3 | 3 | 0 | 0 | 0.09 | 0.08 | 92% |
| 16 | Construction of Percolation Tank | 2 | 0 | 0 | 0 | 0.04 | 0.00 | 0% |
| 17 | Construction of Crematorium | 2 | 0 | 2 | 0 | 0.04 | 0.04 | 101% |
| 18 | Culvert | 2 | 1 | 0 | 1 | 0.29 | 0.00 | 2% |
| 19 | Repair & maint of Pond/ Tank | 2 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| 20 | Constr of Aganwadi | 1 | 1 | 0 | 0 | 0.03 | 0.03 | 105% |
| 21 | Construction of Play field | 1 | 0 | 1 | 0 | 0.02 | 0.01 | 96% |
| 22 | Community Sanitary Complex | 1 | 0 | 1 | 0 | 0.00 | 0.00 | 96% |
| 23 | Terracing | 1 | 0 | 0 | 0 | 0.05 | 0.06 | 122% |
| 24 | Deepening / Desilting of Flood Channels | 1 | 0 | 0 | 0 | 0.12 | 0.00 | 0% |
| Total | 217 | 21 | 85 | 54 | 6.83 | 4.38 |