| Sr. | New Work Type | Total works | Ongoing | Completed | Closed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|---|---|---|
| 1 | Rural Housing | 31 | 3 | 24 | 0 | 0.05 | 0.04 | 78% |
| 2 | Cattle Shed | 17 | 2 | 8 | 0 | 0.10 | 0.05 | 56% |
| 3 | Construction of Check Dam/Stop Dam | 15 | 5 | 4 | 1 | 1.42 | 0.66 | 47% |
| 4 | Constr of Cement Concrete Roads | 12 | 0 | 11 | 0 | 0.10 | 0.11 | 105% |
| 5 | Construction of Water Drain/Diversion Channel/Drainage/Field Channel | 12 | 2 | 3 | 1 | 0.35 | 0.15 | 44% |
| 6 | Land Development | 9 | 0 | 6 | 1 | 0.27 | 0.02 | 7% |
| 7 | Plantation | 9 | 2 | 3 | 1 | 0.15 | 0.01 | 6% |
| 8 | Works for Flood Control and Protection | 6 | 0 | 1 | 1 | 0.27 | 0.17 | 64% |
| 9 | Construction of Bund | 6 | 0 | 4 | 1 | 0.15 | 0.01 | 8% |
| 10 | Repair & maint of Pond/ Tank | 6 | 0 | 3 | 0 | 0.00 | 0.00 | 49% |
| 11 | Solid and Liquid Waste Management | 6 | 0 | 1 | 0 | 0.00 | 0.00 | 35% |
| 12 | Construction of Trench | 4 | 0 | 2 | 0 | 0.11 | 0.10 | 87% |
| 13 | Construction of Canal | 4 | 0 | 1 | 0 | 0.05 | 0.04 | 78% |
| 14 | Construction of Tank | 3 | 0 | 1 | 0 | 0.02 | 0.01 | 73% |
| 15 | Construction of NADEP/Vermi Compost Pit | 3 | 0 | 3 | 0 | 0.01 | 0.00 | 33% |
| 16 | Construction of Play field | 3 | 0 | 2 | 0 | 0.06 | 0.03 | 46% |
| 17 | Construction of Road and Culvert | 2 | 0 | 2 | 0 | 0.24 | 0.22 | 90% |
| 18 | Farm Pond | 2 | 0 | 0 | 0 | 0.03 | 0.02 | 71% |
| 19 | Construction of Percolation Tank | 2 | 0 | 0 | 0 | 0.03 | 0.00 | 0% |
| 20 | Construction of Crematorium | 2 | 0 | 2 | 0 | 0.15 | 0.12 | 81% |
| 21 | Culvert | 1 | 0 | 1 | 0 | 0.02 | 0.02 | 99% |
| 22 | Construction of Well | 1 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| 23 | Lining of Canal | 1 | 0 | 1 | 0 | 0.02 | 0.01 | 59% |
| 24 | Community Sanitary Complex | 1 | 0 | 0 | 0 | 0.00 | 0.00 | 62% |
| 25 | Construction of Toilets | 1 | 0 | 1 | 0 | 0.00 | 0.00 | 100% |
| Total | 159 | 14 | 84 | 6 | 3.61 | 1.81 |