| Sr. | New Work Type | Total works | Ongoing | Completed | Closed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|---|---|---|
| 1 | Construction of Toilets | 118 | 0 | 48 | 0 | 5.31 | 1.81 | 34% |
| 2 | Land Development | 45 | 0 | 13 | 1 | 12.59 | 3.79 | 30% |
| 3 | Cattle Shed | 29 | 0 | 3 | 0 | 29.50 | 29.28 | 99% |
| 4 | Farm Pond | 21 | 3 | 4 | 3 | 28.17 | 9.80 | 35% |
| 5 | Constr of Cement Concrete Roads | 20 | 0 | 14 | 2 | 12.26 | 9.95 | 81% |
| 6 | Construction of Bund | 18 | 0 | 0 | 5 | 49.91 | 5.75 | 12% |
| 7 | Construction of Check Dam/Stop Dam | 13 | 0 | 6 | 3 | 65.17 | 57.60 | 88% |
| 8 | Construction of Road and Culvert | 11 | 0 | 2 | 2 | 54.03 | 36.00 | 67% |
| 9 | Construction of Tank | 11 | 1 | 1 | 2 | 27.66 | 10.84 | 39% |
| 10 | Plantation | 9 | 0 | 3 | 5 | 23.66 | 0.94 | 4% |
| 11 | Rural Housing | 9 | 1 | 8 | 0 | 1.76 | 1.54 | 87% |
| 12 | Repair & maint of Pond/ Tank | 8 | 0 | 2 | 2 | 10.10 | 9.09 | 90% |
| 13 | Terracing | 7 | 0 | 1 | 6 | 7.36 | 6.59 | 90% |
| 14 | Construction of Water Drain/Diversion Channel/Drainage/Field Channel | 5 | 0 | 2 | 0 | 26.31 | 24.12 | 92% |
| 15 | Construction of Crematorium | 4 | 0 | 2 | 0 | 5.40 | 3.75 | 70% |
| 16 | Works for Flood Control and Protection | 4 | 0 | 0 | 2 | 19.10 | 1.37 | 7% |
| 17 | Construction of Play field | 4 | 0 | 2 | 0 | 4.60 | 2.29 | 50% |
| 18 | Construction of Trench | 4 | 1 | 0 | 1 | 14.79 | 0.18 | 1% |
| 19 | Construction of Percolation Tank | 4 | 0 | 0 | 2 | 0.00 | 0.00 | 0% |
| 20 | Construction of Well | 3 | 0 | 0 | 2 | 0.00 | 0.00 | 0% |
| 21 | Construction of Other Community Building/Assets | 3 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| 22 | Construction of NADEP/Vermi Compost Pit | 3 | 0 | 2 | 1 | 1.20 | 0.60 | 50% |
| 23 | Constr of GP Bhawan | 2 | 0 | 2 | 0 | 13.90 | 6.09 | 44% |
| 24 | Constr of Aganwadi | 1 | 0 | 1 | 0 | 1.80 | 1.76 | 98% |
| 25 | Repair & maint of Water Harvesting Structures | 1 | 0 | 1 | 0 | 14.00 | 13.16 | 94% |
| 26 | Community Sanitary Complex | 1 | 0 | 1 | 0 | 0.43 | 0.41 | 95% |
| 27 | Solid and Liquid Waste Management | 1 | 0 | 1 | 0 | 0.68 | 0.44 | 65% |
| 28 | Constr of Kitchen Shed | 1 | 0 | 0 | 1 | 4.25 | 0.00 | 0% |
| 29 | Construction of Recharge Pits | 1 | 0 | 1 | 0 | 0.98 | 0.97 | 99% |
| Total | 361 | 6 | 120 | 40 | 434.91 | 238.13 |