| Sr. | New Work Type | Total works | Ongoing | Completed | Closed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|---|---|---|
| 1 | Constr of Cement Concrete Roads | 58 | 1 | 34 | 11 | 23.01 | 18.05 | 78% |
| 2 | Rural Housing | 32 | 0 | 32 | 0 | 6.01 | 5.65 | 94% |
| 3 | Construction of NADEP/Vermi Compost Pit | 27 | 0 | 15 | 1 | 3.10 | 1.67 | 54% |
| 4 | Land Development | 22 | 0 | 5 | 15 | 7.74 | 1.26 | 16% |
| 5 | Construction of Bund | 18 | 0 | 4 | 14 | 10.40 | 8.50 | 82% |
| 6 | Construction of Road and Culvert | 18 | 1 | 7 | 4 | 64.33 | 15.20 | 24% |
| 7 | Farm Pond | 17 | 0 | 8 | 7 | 12.73 | 3.73 | 29% |
| 8 | Construction of Toilets | 16 | 0 | 16 | 0 | 0.93 | 0.91 | 98% |
| 9 | Construction of Check Dam/Stop Dam | 11 | 0 | 9 | 2 | 8.44 | 7.09 | 84% |
| 10 | Construction of Water Drain/Diversion Channel/Drainage/Field Channel | 8 | 0 | 2 | 6 | 2.92 | 1.67 | 57% |
| 11 | Well Recharge | 6 | 0 | 2 | 0 | 0.78 | 0.49 | 64% |
| 12 | Construction of Tank | 6 | 0 | 3 | 3 | 29.64 | 19.65 | 66% |
| 13 | Construction of Trench | 6 | 0 | 4 | 2 | 3.08 | 2.15 | 70% |
| 14 | Repair & maint of Pond/ Tank | 5 | 0 | 3 | 1 | 5.82 | 3.95 | 68% |
| 15 | Plantation | 5 | 1 | 1 | 2 | 18.19 | 2.95 | 16% |
| 16 | Cattle Shed | 3 | 0 | 3 | 0 | 2.52 | 1.98 | 79% |
| 17 | Constr of Aganwadi | 3 | 0 | 2 | 1 | 11.87 | 0.97 | 8% |
| 18 | Construction of Recharge Pits | 3 | 0 | 0 | 1 | 1.01 | 0.00 | 0% |
| 19 | Constr of GP Bhawan | 3 | 0 | 2 | 1 | 1.82 | 1.78 | 98% |
| 20 | Constr of Kitchen Shed | 2 | 0 | 0 | 2 | 0.40 | 0.00 | 0% |
| 21 | Constr of Food Grain storage | 2 | 0 | 1 | 1 | 16.48 | 7.97 | 48% |
| 22 | Construction of Well | 2 | 0 | 2 | 0 | 0.67 | 0.41 | 61% |
| 23 | Culvert | 2 | 0 | 2 | 0 | 4.40 | 3.94 | 90% |
| 24 | Repaire and Maint of NADEP/Vermi Compost Pit | 2 | 0 | 0 | 2 | 0.00 | 0.00 | 0% |
| 25 | Construction of Canal | 2 | 0 | 0 | 2 | 0.00 | 0.00 | 0% |
| 26 | Community Sanitary Complex | 1 | 0 | 1 | 0 | 0.45 | 0.34 | 75% |
| 27 | Underground Dyke for Ground Water Recharge | 1 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| 28 | Construction of Crematorium | 1 | 0 | 1 | 0 | 1.80 | 1.88 | 105% |
| 29 | Repair & Maint of Community infrastructure | 1 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| 30 | Construction of Spur | 1 | 0 | 0 | 1 | 0.41 | 0.00 | 0% |
| 31 | Repair & maint of Road | 1 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| 32 | Roof Water Harvesting on gov/panchayat bldg | 1 | 0 | 0 | 1 | 0.41 | 0.00 | 0% |
| 33 | Constr of Compound wall | 1 | 0 | 1 | 0 | 5.11 | 5.08 | 100% |
| 34 | Construction of Play field | 1 | 0 | 1 | 0 | 1.87 | 0.69 | 37% |
| 35 | Solid and Liquid Waste Management | 1 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| 36 | Boulder Check/Gully Plug | 1 | 0 | 1 | 0 | 2.98 | 2.16 | 73% |
| Total | 290 | 3 | 162 | 83 | 249.31 | 120.14 |