| Sr. | New Work Type | Total works | Ongoing | Completed | Closed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|---|---|---|
| 1 | Rural Housing | 288 | 14 | 230 | 1 | 0.57 | 0.50 | 88% |
| 2 | Construction of Toilets | 166 | 0 | 81 | 0 | 0.07 | 0.04 | 52% |
| 3 | Construction of Trench | 37 | 0 | 33 | 0 | 0.33 | 0.29 | 87% |
| 4 | Construction of Check Dam/Stop Dam | 31 | 0 | 26 | 4 | 0.49 | 0.62 | 125% |
| 5 | Construction of Bund | 22 | 0 | 14 | 8 | 0.04 | 0.03 | 79% |
| 6 | Construction of Well | 21 | 1 | 11 | 3 | 0.58 | 0.32 | 56% |
| 7 | Construction of Road and Culvert | 19 | 0 | 17 | 1 | 1.22 | 1.15 | 94% |
| 8 | Plantation | 16 | 2 | 2 | 11 | 0.16 | 0.03 | 17% |
| 9 | Farm Pond | 10 | 0 | 2 | 2 | 0.13 | 0.07 | 53% |
| 10 | Culvert | 10 | 0 | 8 | 0 | 0.44 | 0.35 | 81% |
| 11 | Well Recharge | 9 | 0 | 9 | 0 | 0.17 | 0.15 | 94% |
| 12 | Constr of Cement Concrete Roads | 9 | 0 | 7 | 1 | 0.14 | 0.12 | 85% |
| 13 | Construction of Percolation Tank | 8 | 0 | 3 | 3 | 0.29 | 0.14 | 50% |
| 14 | Land Development | 6 | 0 | 4 | 1 | 0.15 | 0.11 | 75% |
| 15 | Construction of Tank | 5 | 0 | 1 | 0 | 0.23 | 0.09 | 37% |
| 16 | Constr of Aganwadi | 2 | 0 | 2 | 0 | 0.04 | 0.04 | 101% |
| 17 | Repair & maint of Percolation Tank | 2 | 0 | 1 | 1 | 0.19 | 0.09 | 48% |
| 18 | Repair & Maint of Community infrastructure | 1 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| 19 | Community Sanitary Complex | 1 | 0 | 1 | 0 | 0.00 | 0.00 | 84% |
| 20 | Boulder Check/Gully Plug | 1 | 0 | 0 | 0 | 0.03 | 0.00 | 0% |
| 21 | Construction of Recharge Pits | 1 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| 22 | Construction of Play field | 1 | 0 | 1 | 0 | 0.04 | 0.04 | 100% |
| 23 | Constr of GP Bhawan | 1 | 0 | 1 | 0 | 0.13 | 0.10 | 76% |
| 24 | Other Works | 1 | 0 | 1 | 0 | 0.05 | 0.04 | 71% |
| Total | 668 | 17 | 455 | 37 | 5.48 | 4.31 |