| Sr. | New Work Type | Total works | Ongoing | Completed | Closed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|---|---|---|
| 1 | Construction of Check Dam/Stop Dam | 130 | 1 | 96 | 27 | 3.81 | 3.55 | 93% |
| 2 | Rural Housing | 106 | 2 | 102 | 0 | 0.18 | 0.17 | 96% |
| 3 | Construction of Percolation Tank | 94 | 0 | 56 | 38 | 2.18 | 1.90 | 87% |
| 4 | Construction of Bund | 63 | 0 | 21 | 30 | 1.48 | 1.34 | 91% |
| 5 | Farm Pond | 57 | 0 | 23 | 0 | 1.37 | 1.27 | 92% |
| 6 | Construction of Tank | 52 | 0 | 8 | 0 | 1.47 | 1.36 | 93% |
| 7 | Land Development | 51 | 0 | 44 | 0 | 0.17 | 0.14 | 85% |
| 8 | Constr of Cement Concrete Roads | 44 | 0 | 27 | 4 | 0.62 | 0.60 | 98% |
| 9 | Construction of Well | 23 | 0 | 18 | 2 | 0.46 | 0.34 | 74% |
| 10 | Construction of Road and Culvert | 22 | 0 | 18 | 4 | 1.12 | 0.88 | 79% |
| 11 | Construction of Trench | 18 | 0 | 7 | 0 | 0.17 | 0.10 | 61% |
| 12 | Plantation | 17 | 1 | 4 | 2 | 0.14 | 0.00 | 1% |
| 13 | Well Recharge | 8 | 0 | 7 | 0 | 0.06 | 0.05 | 89% |
| 14 | Constr of GP Bhawan | 5 | 0 | 0 | 3 | 0.00 | 0.00 | 8% |
| 15 | Construction of Water Drain/Diversion Channel/Drainage/Field Channel | 5 | 0 | 5 | 0 | 0.06 | 0.06 | 100% |
| 16 | Construction of Recharge Pits | 5 | 0 | 5 | 0 | 0.06 | 0.06 | 86% |
| 17 | Solid and Liquid Waste Management | 3 | 0 | 0 | 3 | 0.00 | 0.00 | 0% |
| 18 | Construction of NADEP/Vermi Compost Pit | 3 | 0 | 0 | 3 | 0.00 | 0.00 | 0% |
| 19 | Cattle Shed | 2 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| 20 | Construction of Play field | 2 | 0 | 2 | 0 | 0.04 | 0.02 | 41% |
| 21 | Repair & maint of Percolation Tank | 2 | 0 | 2 | 0 | 0.01 | 0.00 | 64% |
| 22 | Repair & maint of Road | 2 | 0 | 1 | 1 | 0.07 | 0.07 | 100% |
| 23 | Constr of Aganwadi | 2 | 0 | 2 | 0 | 0.06 | 0.05 | 75% |
| 24 | Renovation of traditional water bodies | 1 | 0 | 1 | 0 | 0.01 | 0.01 | 82% |
| 25 | Grass Land Development | 1 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| 26 | Constr of Gabion | 1 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| Total | 719 | 4 | 449 | 120 | 13.53 | 11.97 |