| Sr. | New Work Type | Total works | Ongoing | Completed | Closed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|---|---|---|
| 1 | Rural Housing | 205 | 10 | 188 | 1 | 35.72 | 34.05 | 95% |
| 2 | Land Development | 52 | 0 | 30 | 8 | 19.04 | 15.24 | 80% |
| 3 | Construction of Toilets | 37 | 0 | 27 | 10 | 4.32 | 3.25 | 75% |
| 4 | Farm Pond | 28 | 0 | 20 | 1 | 18.06 | 10.14 | 56% |
| 5 | Construction of NADEP/Vermi Compost Pit | 23 | 0 | 18 | 3 | 2.88 | 2.08 | 72% |
| 6 | Construction of Bund | 20 | 0 | 17 | 1 | 7.04 | 5.10 | 72% |
| 7 | Construction of Well | 20 | 0 | 11 | 7 | 34.57 | 28.20 | 82% |
| 8 | Constr of Cement Concrete Roads | 18 | 0 | 16 | 1 | 18.46 | 16.51 | 90% |
| 9 | Construction of Road and Culvert | 15 | 0 | 7 | 8 | 45.77 | 28.06 | 61% |
| 10 | Plantation | 14 | 0 | 10 | 3 | 19.05 | 4.75 | 25% |
| 11 | Well Recharge | 9 | 0 | 0 | 0 | 2.18 | 2.05 | 94% |
| 12 | Solid and Liquid Waste Management | 4 | 0 | 4 | 0 | 1.15 | 1.10 | 96% |
| 13 | Construction of Recharge Pits | 3 | 0 | 2 | 1 | 3.77 | 2.57 | 68% |
| 14 | Repair & maint of Pond/ Tank | 2 | 0 | 1 | 1 | 4.43 | 4.42 | 100% |
| 15 | Construction of Percolation Tank | 2 | 0 | 2 | 0 | 1.84 | 1.99 | 108% |
| 16 | Construction of Check Dam/Stop Dam | 2 | 0 | 1 | 0 | 1.00 | 1.30 | 130% |
| 17 | Constr of Compound wall | 2 | 0 | 1 | 0 | 0.67 | 0.16 | 24% |
| 18 | Terracing | 1 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| 19 | Construction of Tank | 1 | 0 | 0 | 0 | 3.34 | 1.59 | 48% |
| 20 | Community Sanitary Complex | 1 | 0 | 1 | 0 | 0.45 | 0.44 | 98% |
| 21 | Construction of Trench | 1 | 0 | 1 | 0 | 0.43 | 0.41 | 95% |
| 22 | Deepening / Desilting of Flood Channels | 1 | 0 | 1 | 0 | 3.47 | 2.47 | 71% |
| 23 | Construction of Crematorium | 1 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| 24 | Roof Water Harvesting on gov/panchayat bldg | 1 | 0 | 1 | 0 | 0.37 | 0.37 | 98% |
| 25 | Constr of Aganwadi | 1 | 0 | 1 | 0 | 0.22 | 0.21 | 100% |
| Total | 464 | 10 | 360 | 46 | 228.22 | 166.47 |