| Sr. | New Work Type | Total works | Ongoing | Completed | Closed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|---|---|---|
| 1 | Rural Housing | 249 | 3 | 238 | 0 | 43.70 | 41.92 | 96% |
| 2 | Plantation | 56 | 2 | 27 | 2 | 62.08 | 13.80 | 22% |
| 3 | Construction of Well | 38 | 2 | 24 | 1 | 64.66 | 35.33 | 55% |
| 4 | Solid and Liquid Waste Management | 24 | 0 | 24 | 0 | 2.31 | 2.28 | 99% |
| 5 | Farm Pond | 20 | 1 | 9 | 2 | 18.35 | 8.98 | 49% |
| 6 | Land Development | 19 | 0 | 13 | 2 | 7.66 | 2.95 | 39% |
| 7 | Constr of Cement Concrete Roads | 18 | 0 | 11 | 2 | 11.50 | 9.23 | 80% |
| 8 | Well Recharge | 16 | 0 | 5 | 0 | 12.37 | 10.74 | 87% |
| 9 | Construction of Road and Culvert | 14 | 0 | 11 | 0 | 85.51 | 30.96 | 36% |
| 10 | Construction of Recharge Pits | 13 | 0 | 5 | 0 | 4.26 | 3.73 | 88% |
| 11 | Construction of Check Dam/Stop Dam | 10 | 1 | 4 | 0 | 32.50 | 4.43 | 14% |
| 12 | Other Works | 10 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| 13 | Construction of Toilets | 9 | 0 | 8 | 0 | 1.71 | 1.55 | 91% |
| 14 | Construction of Tank | 6 | 0 | 2 | 1 | 47.58 | 39.54 | 83% |
| 15 | Cattle Shed | 6 | 0 | 2 | 0 | 3.85 | 2.64 | 68% |
| 16 | Constr of Gabion | 4 | 0 | 2 | 0 | 0.67 | 0.62 | 91% |
| 17 | Constr of Aganwadi | 3 | 0 | 2 | 0 | 3.65 | 1.45 | 40% |
| 18 | Construction of Play field | 3 | 0 | 1 | 0 | 5.61 | 1.36 | 24% |
| 19 | Construction of Crematorium | 3 | 0 | 2 | 0 | 5.40 | 3.51 | 65% |
| 20 | Construction of Bund | 3 | 0 | 3 | 0 | 1.00 | 0.84 | 84% |
| 21 | Constr of GP Bhawan | 3 | 0 | 3 | 0 | 15.58 | 13.24 | 85% |
| 22 | Construction of NADEP/Vermi Compost Pit | 2 | 0 | 1 | 0 | 0.65 | 0.50 | 77% |
| 23 | Construction of Trench | 2 | 0 | 2 | 0 | 0.09 | 0.08 | 95% |
| 24 | Constr of Compound wall | 2 | 0 | 2 | 0 | 0.32 | 0.03 | 11% |
| 25 | Repair & maint of Pond/ Tank | 2 | 0 | 2 | 0 | 5.66 | 1.58 | 28% |
| 26 | Repair & Maint of Community infrastructure | 2 | 0 | 2 | 0 | 16.37 | 4.78 | 29% |
| 27 | Repair & maint of Water Harvesting Structures | 1 | 0 | 1 | 0 | 0.14 | 0.09 | 65% |
| 28 | Construction of Embankment | 1 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| 29 | Construction of Percolation Tank | 1 | 0 | 1 | 0 | 0.14 | 0.10 | 69% |
| Total | 540 | 9 | 407 | 11 | 453.31 | 236.25 |