| Sr. | New Work Type | Total works | Ongoing | Completed | Closed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|---|---|---|
| 1 | Rural Housing | 391 | 0 | 375 | 0 | 65.77 | 60.03 | 91% |
| 2 | Construction of Toilets | 202 | 0 | 165 | 0 | 9.37 | 7.97 | 85% |
| 3 | Constr of Cement Concrete Roads | 54 | 2 | 45 | 3 | 46.10 | 38.28 | 83% |
| 4 | Construction of NADEP/Vermi Compost Pit | 31 | 1 | 11 | 19 | 0.94 | 0.31 | 33% |
| 5 | Plantation | 30 | 0 | 10 | 6 | 52.65 | 16.97 | 32% |
| 6 | Cattle Shed | 20 | 0 | 18 | 0 | 39.17 | 35.01 | 89% |
| 7 | Construction of Bund | 15 | 1 | 1 | 10 | 11.80 | 3.25 | 28% |
| 8 | Solid and Liquid Waste Management | 14 | 0 | 4 | 10 | 6.76 | 4.61 | 68% |
| 9 | Construction of Well | 13 | 0 | 7 | 5 | 22.90 | 15.54 | 68% |
| 10 | Farm Pond | 11 | 3 | 2 | 0 | 11.89 | 3.47 | 29% |
| 11 | Construction of Check Dam/Stop Dam | 10 | 0 | 8 | 0 | 53.50 | 20.62 | 39% |
| 12 | Terracing | 8 | 0 | 0 | 5 | 2.17 | 0.03 | 2% |
| 13 | Construction of Recharge Pits | 8 | 0 | 6 | 2 | 0.86 | 0.85 | 99% |
| 14 | Construction of Road and Culvert | 6 | 0 | 4 | 0 | 12.37 | 8.04 | 65% |
| 15 | Land Development | 6 | 0 | 5 | 0 | 3.27 | 0.63 | 19% |
| 16 | Well Recharge | 5 | 0 | 3 | 0 | 0.78 | 0.01 | 1% |
| 17 | Construction of Percolation Tank | 4 | 0 | 2 | 1 | 0.48 | 0.42 | 88% |
| 18 | Roof Water Harvesting on gov/panchayat bldg | 4 | 0 | 4 | 0 | 0.89 | 0.80 | 90% |
| 19 | Constr of GP Bhawan | 4 | 1 | 1 | 2 | 15.95 | 6.03 | 38% |
| 20 | Constr of Food Grain storage | 3 | 0 | 1 | 0 | 4.28 | 1.25 | 29% |
| 21 | Construction of Trench | 3 | 0 | 1 | 0 | 4.15 | 1.25 | 30% |
| 22 | Constr of Aganwadi | 2 | 0 | 1 | 1 | 11.63 | 11.64 | 100% |
| 23 | Repair & maint of Pond/ Tank | 2 | 0 | 2 | 0 | 4.74 | 4.00 | 84% |
| 24 | Constr of Compound wall | 1 | 0 | 1 | 0 | 0.76 | 0.76 | 100% |
| 25 | Community Sanitary Complex | 1 | 0 | 1 | 0 | 0.75 | 0.73 | 97% |
| 26 | Construction of Play field | 1 | 0 | 0 | 1 | 3.53 | 0.00 | 0% |
| 27 | Bio-Fertilizer | 1 | 0 | 0 | 1 | 1.44 | 0.00 | 0% |
| 28 | Construction of Village Haats | 1 | 0 | 1 | 0 | 1.05 | 1.04 | 99% |
| 29 | Construction of Water Drain/Diversion Channel/Drainage/Field Channel | 1 | 0 | 1 | 0 | 3.96 | 3.96 | 100% |
| 30 | Construction of Crematorium | 1 | 0 | 0 | 0 | 1.80 | 0.00 | 0% |
| 31 | Culvert | 1 | 0 | 1 | 0 | 2.60 | 2.61 | 101% |
| 32 | Construction of Canal | 1 | 0 | 1 | 0 | 5.77 | 5.52 | 96% |
| 33 | Grass Land Development | 1 | 0 | 1 | 0 | 7.51 | 0.21 | 3% |
| Total | 856 | 8 | 683 | 66 | 411.57 | 255.83 |