| Sr. | New Work Type | Total works | Ongoing | Completed | Closed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|---|---|---|
| 1 | Rural Housing | 337 | 10 | 290 | 0 | 64.48 | 55.22 | 86% |
| 2 | Construction of Toilets | 95 | 0 | 88 | 0 | 8.04 | 8.48 | 106% |
| 3 | Constr of Cement Concrete Roads | 27 | 1 | 19 | 1 | 46.69 | 18.83 | 40% |
| 4 | Construction of Bund | 24 | 0 | 13 | 7 | 15.90 | 4.89 | 31% |
| 5 | Plantation | 21 | 8 | 4 | 6 | 31.35 | 5.10 | 16% |
| 6 | Land Development | 17 | 0 | 12 | 0 | 5.59 | 3.17 | 57% |
| 7 | Construction of Well | 12 | 2 | 6 | 0 | 21.18 | 14.85 | 70% |
| 8 | Construction of NADEP/Vermi Compost Pit | 10 | 0 | 3 | 7 | 0.49 | 0.38 | 78% |
| 9 | Construction of Recharge Pits | 7 | 0 | 4 | 3 | 0.55 | 0.19 | 35% |
| 10 | Construction of Road and Culvert | 7 | 1 | 4 | 1 | 48.07 | 24.36 | 51% |
| 11 | Farm Pond | 7 | 1 | 2 | 0 | 8.07 | 1.60 | 20% |
| 12 | Construction of Check Dam/Stop Dam | 6 | 0 | 6 | 0 | 10.37 | 8.25 | 80% |
| 13 | Works for Flood Control and Protection | 3 | 2 | 1 | 0 | 1.41 | 0.82 | 58% |
| 14 | Culvert | 3 | 0 | 3 | 0 | 0.82 | 0.62 | 76% |
| 15 | Constr of Aganwadi | 2 | 0 | 1 | 1 | 3.80 | 1.33 | 35% |
| 16 | Cattle Shed | 2 | 1 | 0 | 1 | 0.64 | 0.60 | 94% |
| 17 | Renovation of traditional water bodies | 1 | 0 | 1 | 0 | 0.76 | 1.64 | 217% |
| 18 | Construction of Water Drain/Diversion Channel/Drainage/Field Channel | 1 | 0 | 0 | 0 | 2.30 | 0.00 | 0% |
| 19 | Terracing | 1 | 0 | 0 | 0 | 1.80 | 0.00 | 0% |
| 20 | Well Recharge | 1 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| 21 | Solid and Liquid Waste Management | 1 | 0 | 1 | 0 | 0.60 | 0.48 | 80% |
| 22 | Construction of Crematorium | 1 | 0 | 0 | 0 | 0.31 | 0.00 | 0% |
| Total | 586 | 26 | 458 | 28 | 273.22 | 150.83 |