| Sr. | New Work Type | Total works | Ongoing | Completed | Closed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|---|---|---|
| 1 | Rural Housing | 244 | 38 | 131 | 0 | 0.50 | 0.31 | 62% |
| 2 | Construction of Toilets | 82 | 1 | 81 | 0 | 0.07 | 0.07 | 94% |
| 3 | Construction of Bund | 45 | 0 | 22 | 22 | 0.17 | 0.14 | 82% |
| 4 | Plantation | 24 | 5 | 1 | 3 | 0.36 | 0.06 | 16% |
| 5 | Constr of Cement Concrete Roads | 16 | 0 | 10 | 4 | 0.26 | 0.10 | 36% |
| 6 | Construction of NADEP/Vermi Compost Pit | 13 | 0 | 6 | 6 | 0.01 | 0.01 | 97% |
| 7 | Cattle Shed | 12 | 0 | 2 | 7 | 0.02 | 0.01 | 43% |
| 8 | Construction of Road and Culvert | 11 | 1 | 7 | 3 | 1.86 | 0.91 | 49% |
| 9 | Solid and Liquid Waste Management | 9 | 0 | 2 | 3 | 0.04 | 0.01 | 24% |
| 10 | Land Development | 7 | 0 | 4 | 2 | 0.03 | 0.03 | 89% |
| 11 | Renovation of traditional water bodies | 6 | 0 | 0 | 0 | 0.05 | 0.04 | 84% |
| 12 | Constr of Aganwadi | 6 | 1 | 0 | 0 | 0.16 | 0.01 | 4% |
| 13 | Construction of Water Drain/Diversion Channel/Drainage/Field Channel | 6 | 0 | 2 | 4 | 0.02 | 0.00 | 28% |
| 14 | Farm Pond | 5 | 0 | 2 | 1 | 0.09 | 0.02 | 18% |
| 15 | Construction of Check Dam/Stop Dam | 5 | 0 | 2 | 2 | 0.08 | 0.05 | 57% |
| 16 | Construction of Well | 5 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| 17 | Repair & maint of Pond/ Tank | 4 | 0 | 4 | 0 | 0.17 | 0.12 | 69% |
| 18 | Goat Shelter | 4 | 1 | 0 | 2 | 0.01 | 0.01 | 83% |
| 19 | Constr of Food Grain storage | 4 | 0 | 0 | 4 | 0.03 | 0.00 | 0% |
| 20 | Works for Flood Control and Protection | 3 | 0 | 0 | 0 | 0.02 | 0.01 | 30% |
| 21 | Repair & Maint of Community infrastructure | 2 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| 22 | Terracing | 2 | 0 | 0 | 2 | 0.00 | 0.00 | 0% |
| 23 | Constr of Gabion | 2 | 0 | 2 | 0 | 0.00 | 0.00 | 101% |
| 24 | Repair & Maint of Check Dam/Stop Dam | 2 | 1 | 0 | 1 | 0.18 | 0.01 | 5% |
| 25 | Constr of GP Bhawan | 2 | 0 | 2 | 0 | 0.01 | 0.01 | 97% |
| 26 | Other Works | 2 | 0 | 0 | 2 | 0.00 | 0.00 | 0% |
| 27 | Construction of Crematorium | 2 | 0 | 2 | 0 | 0.06 | 0.06 | 92% |
| 28 | Construction of Trench | 1 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| 29 | Construction of Other Community Building/Assets | 1 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| 30 | Construction of Percolation Tank | 1 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| 31 | Construction of Recharge Pits | 1 | 0 | 1 | 0 | 0.00 | 0.00 | 92% |
| 32 | Construction of Tank | 1 | 0 | 1 | 0 | 0.03 | 0.02 | 68% |
| 33 | Bio-Fertilizer | 1 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| 34 | Culvert | 1 | 0 | 1 | 0 | 0.00 | 0.00 | 90% |
| 35 | Underground Dyke for Ground Water Recharge | 1 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| Total | 533 | 48 | 285 | 71 | 4.24 | 1.98 |