| Sr. | New Work Type | Total works | Ongoing | Completed | Closed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|---|---|---|
| 1 | Rural Housing | 198 | 33 | 47 | 1 | 43.49 | 15.16 | 35% |
| 2 | Construction of Toilets | 50 | 0 | 43 | 4 | 4.48 | 3.68 | 82% |
| 3 | Constr of Cement Concrete Roads | 46 | 2 | 36 | 2 | 24.12 | 20.41 | 85% |
| 4 | Construction of Check Dam/Stop Dam | 38 | 0 | 27 | 1 | 74.63 | 52.39 | 70% |
| 5 | Plantation | 29 | 4 | 13 | 5 | 76.67 | 19.60 | 26% |
| 6 | Construction of Well | 12 | 0 | 11 | 0 | 35.02 | 34.35 | 98% |
| 7 | Farm Pond | 11 | 0 | 4 | 1 | 9.30 | 4.96 | 53% |
| 8 | Construction of Road and Culvert | 10 | 0 | 9 | 1 | 83.44 | 76.92 | 92% |
| 9 | Well Recharge | 9 | 0 | 2 | 0 | 2.27 | 1.66 | 73% |
| 10 | Constr of GP Bhawan | 6 | 0 | 2 | 4 | 0.80 | 0.02 | 3% |
| 11 | Repair & maint of Pond/ Tank | 5 | 0 | 3 | 2 | 14.69 | 8.92 | 61% |
| 12 | Land Development | 5 | 0 | 5 | 0 | 5.16 | 5.06 | 98% |
| 13 | Cattle Shed | 5 | 0 | 3 | 0 | 38.45 | 37.76 | 98% |
| 14 | Repair & Maint of Check Dam/Stop Dam | 4 | 0 | 4 | 0 | 11.93 | 11.78 | 99% |
| 15 | Construction of Trench | 3 | 0 | 2 | 1 | 5.03 | 4.25 | 85% |
| 16 | Construction of Play field | 2 | 0 | 2 | 0 | 5.95 | 5.31 | 89% |
| 17 | Construction of Percolation Tank | 2 | 0 | 1 | 1 | 5.10 | 5.05 | 99% |
| 18 | Grass Land Development | 1 | 1 | 0 | 0 | 15.71 | 8.35 | 53% |
| 19 | Construction of Tank | 1 | 0 | 0 | 0 | 6.34 | 0.00 | 0% |
| 20 | Construction of NADEP/Vermi Compost Pit | 1 | 0 | 0 | 0 | 0.15 | 0.00 | 0% |
| 21 | Construction of Recharge Pits | 1 | 0 | 1 | 0 | 1.09 | 0.86 | 79% |
| 22 | Community Sanitary Complex | 1 | 0 | 1 | 0 | 0.44 | 0.42 | 96% |
| Total | 440 | 40 | 216 | 23 | 464.26 | 316.90 |