MGNREGA Works Dashboard
MGNREGA VBGRAMG MGNREGA + VBGRAMG
Admin login

Overall

Rollup last refreshed: 2026-09-07 06:52:02.404114 · figures are real, from vg_work_summary_rollup
to
to
Reset filters
Total works
160
All statuses · all years
Approved
112
70% of total
Ongoing
46
28.8% of total
Physically Completed
2
1.3% of total
Sanctioned
₹91.59 L
Pure scheme basis
Expenditure %
0.3%
₹23,100 of ₹91.59 L

Detailed breakdown (All amounts in ₹ Lakh)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Total works Ongoing Completed Closed Sanctioned Expenditure Exp. %
1 Rural Housing 145 39 0 0 39.08 0.23
1%
2 Plantation 5 4 0 0 27.66 0.00
0%
3 Constr of Cement Concrete Roads 5 2 0 0 2.24 0.00
0%
4 Well Recharge 2 0 0 0 0.00 0.00
0%
5 Grass Land Development 1 1 0 0 15.71 0.00
0%
6 Construction of Tank 1 0 0 0 6.34 0.00
0%
7 Farm Pond 1 0 0 0 0.56 0.00
0%
Total 160 46 0 0 91.59 0.23
All 7 rows (zero-value rows hidden) ⇩ Export to Excel