| Sr. | New Work Type | Total works | Ongoing | Completed | Closed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|---|---|---|
| 1 | Rural Housing | 307 | 30 | 164 | 3 | 0.65 | 0.36 | 56% |
| 2 | Construction of Toilets | 66 | 0 | 66 | 0 | 0.08 | 0.07 | 87% |
| 3 | Constr of Cement Concrete Roads | 52 | 0 | 33 | 8 | 0.28 | 0.21 | 77% |
| 4 | Construction of Well | 21 | 2 | 8 | 5 | 0.29 | 0.21 | 73% |
| 5 | Well Recharge | 14 | 1 | 1 | 1 | 0.17 | 0.16 | 94% |
| 6 | Land Development | 14 | 1 | 5 | 3 | 0.24 | 0.19 | 80% |
| 7 | Construction of Road and Culvert | 13 | 0 | 7 | 6 | 1.28 | 0.94 | 74% |
| 8 | Plantation | 13 | 4 | 3 | 4 | 0.24 | 0.06 | 25% |
| 9 | Construction of Percolation Tank | 12 | 0 | 7 | 3 | 0.22 | 0.19 | 89% |
| 10 | Construction of Check Dam/Stop Dam | 9 | 0 | 5 | 3 | 0.18 | 0.16 | 88% |
| 11 | Construction of NADEP/Vermi Compost Pit | 8 | 0 | 0 | 2 | 0.00 | 0.00 | 0% |
| 12 | Repair & maint of Pond/ Tank | 7 | 2 | 2 | 2 | 0.11 | 0.05 | 49% |
| 13 | Constr of GP Bhawan | 3 | 0 | 2 | 1 | 0.18 | 0.07 | 40% |
| 14 | Community Sanitary Complex | 3 | 2 | 0 | 1 | 0.01 | 0.01 | 57% |
| 15 | Construction of Bund | 2 | 0 | 1 | 1 | 0.41 | 0.31 | 77% |
| 16 | Construction of Recharge Pits | 2 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| 17 | Cattle Shed | 2 | 1 | 0 | 1 | 0.38 | 0.35 | 92% |
| 18 | Repaire and Maint of NADEP/Vermi Compost Pit | 2 | 0 | 0 | 2 | 0.00 | 0.00 | 0% |
| 19 | Repair & Maint of Bund | 1 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| 20 | Repair & maint of Percolation Tank | 1 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| 21 | Constr of Aganwadi | 1 | 0 | 1 | 0 | 0.05 | 0.05 | 99% |
| 22 | Repair & maint of Road | 1 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| 23 | Construction of Trench | 1 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| 24 | Construction of Crematorium | 1 | 0 | 0 | 1 | 0.02 | 0.00 | 0% |
| Total | 556 | 43 | 305 | 52 | 4.79 | 3.41 |