| Sr. | New Work Type | Total works | Ongoing | Completed | Closed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|---|---|---|
| 1 | Rural Housing | 157 | 18 | 138 | 0 | 33.99 | 29.68 | 87% |
| 2 | Construction of Well | 32 | 3 | 17 | 5 | 47.42 | 39.54 | 83% |
| 3 | Constr of Cement Concrete Roads | 30 | 0 | 16 | 2 | 15.01 | 11.79 | 79% |
| 4 | Well Recharge | 24 | 0 | 10 | 10 | 7.59 | 3.80 | 50% |
| 5 | Construction of Road and Culvert | 16 | 0 | 8 | 2 | 34.78 | 27.20 | 78% |
| 6 | Plantation | 16 | 1 | 3 | 4 | 20.19 | 3.44 | 17% |
| 7 | Land Development | 15 | 0 | 10 | 0 | 9.47 | 4.97 | 52% |
| 8 | Solid and Liquid Waste Management | 10 | 0 | 1 | 9 | 0.57 | 0.55 | 97% |
| 9 | Construction of Bund | 9 | 0 | 5 | 4 | 8.63 | 3.76 | 44% |
| 10 | Farm Pond | 9 | 0 | 1 | 4 | 15.35 | 4.59 | 30% |
| 11 | Construction of Water Drain/Diversion Channel/Drainage/Field Channel | 6 | 0 | 0 | 4 | 6.89 | 0.00 | 0% |
| 12 | Construction of Trench | 4 | 0 | 2 | 1 | 3.46 | 0.18 | 5% |
| 13 | Construction of Tank | 4 | 0 | 0 | 4 | 7.37 | 0.00 | 0% |
| 14 | Construction of Check Dam/Stop Dam | 3 | 0 | 2 | 1 | 4.48 | 3.47 | 77% |
| 15 | Nursery Development | 3 | 0 | 3 | 0 | 3.61 | 0.10 | 3% |
| 16 | Construction of Recharge Pits | 3 | 0 | 1 | 2 | 2.80 | 1.16 | 42% |
| 17 | Constr of GP Bhawan | 3 | 0 | 1 | 1 | 10.28 | 5.03 | 49% |
| 18 | Cattle Shed | 2 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| 19 | Bio-Fertilizer | 2 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| 20 | Repair & maint of Road | 2 | 0 | 1 | 1 | 1.15 | 0.96 | 83% |
| 21 | Other Works | 1 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| 22 | Construction of Percolation Tank | 1 | 0 | 1 | 0 | 0.14 | 0.14 | 99% |
| 23 | Renovation of traditional water bodies | 1 | 0 | 1 | 0 | 0.98 | 0.55 | 56% |
| 24 | Repair & maint of Pond/ Tank | 1 | 0 | 1 | 0 | 1.43 | 1.41 | 99% |
| 25 | Construction of Toilets | 1 | 0 | 1 | 0 | 2.30 | 2.28 | 99% |
| 26 | Repair & maint of Water Harvesting Structures | 1 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| 27 | Constr of Kitchen Shed | 1 | 0 | 0 | 1 | 0.20 | 0.00 | 0% |
| 28 | Construction of Play field | 1 | 0 | 1 | 0 | 4.16 | 3.90 | 94% |
| 29 | Construction of Crematorium | 1 | 0 | 1 | 0 | 5.69 | 3.29 | 58% |
| Total | 359 | 22 | 225 | 56 | 247.95 | 151.80 |