| Sr. | New Work Type | Total works | Ongoing | Completed | Closed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|---|---|---|
| 1 | Rural Housing | 200 | 46 | 125 | 0 | 0.38 | 0.33 | 89% |
| 2 | Construction of Well | 35 | 1 | 25 | 0 | 0.23 | 0.17 | 75% |
| 3 | Farm Pond | 18 | 1 | 12 | 1 | 0.25 | 0.17 | 70% |
| 4 | Construction of Check Dam/Stop Dam | 13 | 0 | 6 | 3 | 1.11 | 0.82 | 74% |
| 5 | Construction of Road and Culvert | 12 | 0 | 10 | 0 | 0.47 | 0.33 | 70% |
| 6 | Construction of Bund | 10 | 0 | 6 | 0 | 0.23 | 0.17 | 75% |
| 7 | Construction of Trench | 10 | 0 | 6 | 2 | 0.39 | 0.21 | 55% |
| 8 | Plantation | 7 | 0 | 5 | 2 | 0.12 | 0.05 | 43% |
| 9 | Boulder Check/Gully Plug | 5 | 0 | 2 | 3 | 0.01 | 0.00 | 19% |
| 10 | Construction of Percolation Tank | 5 | 0 | 0 | 4 | 0.00 | 0.00 | 0% |
| 11 | Constr of Cement Concrete Roads | 5 | 0 | 2 | 0 | 0.02 | 0.03 | 151% |
| 12 | Solid and Liquid Waste Management | 4 | 0 | 0 | 4 | 0.00 | 0.00 | 0% |
| 13 | Well Recharge | 3 | 0 | 1 | 1 | 0.01 | 0.00 | 34% |
| 14 | Constr of Gabion | 2 | 0 | 1 | 0 | 0.11 | 0.10 | 96% |
| 15 | Land Development | 2 | 0 | 1 | 0 | 0.05 | 0.05 | 94% |
| 16 | Constr of Aganwadi | 2 | 0 | 0 | 1 | 0.05 | 0.04 | 80% |
| 17 | Construction of Water Drain/Diversion Channel/Drainage/Field Channel | 1 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| 18 | Roof Water Harvesting on gov/panchayat bldg | 1 | 0 | 1 | 0 | 0.03 | 0.02 | 67% |
| 19 | Constr of Compound wall | 1 | 1 | 0 | 0 | 0.14 | 0.08 | 57% |
| 20 | Construction of Crematorium | 1 | 0 | 0 | 0 | 0.02 | 0.00 | 0% |
| 21 | Construction of Tank | 1 | 0 | 1 | 0 | 0.03 | 0.02 | 83% |
| 22 | Construction of Play field | 1 | 0 | 1 | 0 | 0.05 | 0.04 | 100% |
| Total | 339 | 49 | 205 | 22 | 3.68 | 2.65 |