| Sr. | New Work Type | Total works | Ongoing | Completed | Closed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|---|---|---|
| 1 | Rural Housing | 350 | 20 | 262 | 11 | 68.84 | 48.01 | 70% |
| 2 | Land Development | 102 | 0 | 79 | 0 | 24.87 | 12.68 | 51% |
| 3 | Construction of Well | 89 | 2 | 63 | 0 | 63.90 | 38.59 | 60% |
| 4 | Construction of Bund | 50 | 1 | 13 | 34 | 26.06 | 10.82 | 42% |
| 5 | Construction of Check Dam/Stop Dam | 30 | 0 | 20 | 6 | 18.06 | 14.84 | 82% |
| 6 | Construction of Trench | 27 | 3 | 4 | 18 | 91.81 | 46.80 | 51% |
| 7 | Farm Pond | 23 | 1 | 17 | 0 | 10.62 | 4.41 | 42% |
| 8 | Plantation | 16 | 1 | 8 | 4 | 33.37 | 1.27 | 4% |
| 9 | Construction of Road and Culvert | 13 | 0 | 9 | 1 | 44.50 | 28.11 | 63% |
| 10 | Repair & maint of Pond/ Tank | 10 | 1 | 1 | 8 | 10.91 | 1.42 | 13% |
| 11 | Construction of NADEP/Vermi Compost Pit | 7 | 0 | 0 | 7 | 4.65 | 0.00 | 0% |
| 12 | Construction of Tank | 7 | 3 | 0 | 0 | 25.35 | 10.88 | 43% |
| 13 | Constr of Cement Concrete Roads | 6 | 0 | 6 | 0 | 13.74 | 9.95 | 72% |
| 14 | Construction of Percolation Tank | 3 | 0 | 1 | 0 | 23.56 | 22.88 | 97% |
| 15 | Constr of Gabion | 3 | 0 | 0 | 2 | 5.95 | 0.55 | 9% |
| 16 | Solid and Liquid Waste Management | 2 | 0 | 0 | 2 | 4.32 | 0.00 | 0% |
| 17 | Construction of Play field | 2 | 0 | 1 | 1 | 8.15 | 7.93 | 97% |
| 18 | Construction of Water Drain/Diversion Channel/Drainage/Field Channel | 1 | 0 | 0 | 1 | 0.14 | 0.00 | 0% |
| 19 | Construction of Toilets | 1 | 0 | 1 | 0 | 0.12 | 0.05 | 42% |
| 20 | Construction of Crematorium | 1 | 0 | 1 | 0 | 1.80 | 1.65 | 92% |
| 21 | Constr of GP Bhawan | 1 | 0 | 1 | 0 | 12.85 | 0.47 | 4% |
| 22 | Constr of Compound wall | 1 | 0 | 1 | 0 | 6.90 | 6.30 | 91% |
| 23 | Constr of Aganwadi | 1 | 0 | 1 | 0 | 1.80 | 1.26 | 70% |
| Total | 746 | 32 | 489 | 95 | 502.28 | 268.85 |