| Sr. | New Work Type | Total works | Ongoing | Completed | Closed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|---|---|---|
| 1 | Rural Housing | 332 | 0 | 327 | 1 | 0.59 | 0.50 | 85% |
| 2 | Construction of Well | 78 | 1 | 32 | 11 | 1.11 | 0.82 | 74% |
| 3 | Construction of Road and Culvert | 29 | 0 | 23 | 1 | 1.09 | 0.53 | 49% |
| 4 | Constr of Cement Concrete Roads | 20 | 0 | 15 | 3 | 0.18 | 0.13 | 72% |
| 5 | Construction of Check Dam/Stop Dam | 15 | 0 | 11 | 4 | 0.15 | 0.07 | 51% |
| 6 | Farm Pond | 15 | 0 | 12 | 1 | 0.22 | 0.11 | 52% |
| 7 | Plantation | 12 | 0 | 6 | 3 | 0.24 | 0.02 | 8% |
| 8 | Well Recharge | 8 | 0 | 5 | 0 | 0.08 | 0.06 | 85% |
| 9 | Repair & maint of Pond/ Tank | 7 | 0 | 2 | 3 | 0.24 | 0.12 | 49% |
| 10 | Land Development | 7 | 0 | 3 | 2 | 0.13 | 0.12 | 90% |
| 11 | Solid and Liquid Waste Management | 5 | 0 | 0 | 5 | 0.00 | 0.00 | 0% |
| 12 | Construction of Play field | 4 | 1 | 0 | 2 | 0.05 | 0.04 | 75% |
| 13 | Construction of Tank | 3 | 0 | 1 | 0 | 0.05 | 0.03 | 60% |
| 14 | Construction of Percolation Tank | 3 | 0 | 1 | 1 | 0.03 | 0.03 | 80% |
| 15 | Construction of Crematorium | 2 | 0 | 1 | 0 | 0.04 | 0.02 | 42% |
| 16 | Construction of Trench | 1 | 0 | 1 | 0 | 0.01 | 0.01 | 59% |
| 17 | Community Sanitary Complex | 1 | 0 | 0 | 0 | 0.01 | 0.00 | 0% |
| 18 | Constr of Compound wall | 1 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| 19 | Constr of Kitchen Shed | 1 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| 20 | Construction of Recharge Pits | 1 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| 21 | Cattle Shed | 1 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| 22 | Culvert | 1 | 0 | 1 | 0 | 0.04 | 0.03 | 80% |
| 23 | Repair & maint of Percolation Tank | 1 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| 24 | Strengthening of Embankment | 1 | 0 | 1 | 0 | 0.03 | 0.03 | 94% |
| Total | 549 | 2 | 442 | 41 | 4.29 | 2.67 |