| Sr. | New Work Type | Total works | Ongoing | Completed | Closed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|---|---|---|
| 1 | Rural Housing | 289 | 10 | 274 | 3 | 51.65 | 49.19 | 95% |
| 2 | Construction of Toilets | 65 | 0 | 58 | 1 | 3.55 | 3.07 | 87% |
| 3 | Land Development | 48 | 0 | 11 | 36 | 7.89 | 3.23 | 41% |
| 4 | Plantation | 41 | 11 | 21 | 4 | 81.36 | 32.18 | 40% |
| 5 | Constr of Cement Concrete Roads | 39 | 3 | 29 | 5 | 42.01 | 30.88 | 74% |
| 6 | Farm Pond | 37 | 3 | 17 | 8 | 58.97 | 28.39 | 48% |
| 7 | Construction of Well | 23 | 1 | 11 | 10 | 49.47 | 21.64 | 44% |
| 8 | Construction of Road and Culvert | 12 | 2 | 9 | 1 | 78.75 | 38.42 | 49% |
| 9 | Construction of NADEP/Vermi Compost Pit | 9 | 0 | 0 | 9 | 1.27 | 0.00 | 0% |
| 10 | Construction of Recharge Pits | 6 | 0 | 0 | 6 | 0.72 | 0.00 | 0% |
| 11 | Cattle Shed | 5 | 0 | 0 | 5 | 37.85 | 0.00 | 0% |
| 12 | Underground Dyke for Ground Water Recharge | 5 | 0 | 0 | 5 | 0.00 | 0.00 | 0% |
| 13 | Constr of Kitchen Shed | 4 | 0 | 0 | 4 | 0.00 | 0.00 | 0% |
| 14 | Construction of Play field | 3 | 0 | 2 | 1 | 13.82 | 3.33 | 24% |
| 15 | Construction of Check Dam/Stop Dam | 3 | 0 | 3 | 0 | 0.24 | 0.18 | 76% |
| 16 | Construction of Tank | 2 | 0 | 0 | 2 | 0.57 | 0.00 | 0% |
| 17 | Well Recharge | 2 | 0 | 2 | 0 | 7.69 | 7.35 | 96% |
| 18 | Construction of Crematorium | 2 | 1 | 0 | 0 | 4.00 | 1.75 | 44% |
| 19 | Constr of Aganwadi | 1 | 1 | 0 | 0 | 1.80 | 1.08 | 60% |
| 20 | Construction of Water Drain/Diversion Channel/Drainage/Field Channel | 1 | 1 | 0 | 0 | 0.26 | 0.00 | 0% |
| 21 | Community Sanitary Complex | 1 | 0 | 1 | 0 | 0.44 | 0.42 | 96% |
| 22 | Works for Flood Control and Protection | 1 | 0 | 0 | 1 | 4.04 | 0.00 | 0% |
| 23 | Renovation of traditional water bodies | 1 | 0 | 1 | 0 | 2.82 | 1.67 | 59% |
| 24 | Construction of Percolation Tank | 1 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| 25 | Construction of Bund | 1 | 0 | 0 | 1 | 0.10 | 0.00 | 0% |
| Total | 602 | 33 | 439 | 103 | 449.26 | 222.79 |