| Sr. | New Work Type | Total works | Ongoing | Completed | Closed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|---|---|---|
| 1 | Rural Housing | 189 | 55 | 116 | 0 | 38.77 | 24.46 | 63% |
| 2 | Construction of Well | 31 | 2 | 21 | 3 | 63.76 | 47.69 | 75% |
| 3 | Well Recharge | 29 | 0 | 5 | 4 | 41.91 | 18.14 | 43% |
| 4 | Constr of Cement Concrete Roads | 22 | 0 | 16 | 1 | 27.10 | 13.60 | 50% |
| 5 | Terracing | 14 | 0 | 11 | 3 | 6.95 | 3.96 | 57% |
| 6 | Construction of Road and Culvert | 12 | 0 | 7 | 0 | 55.63 | 24.76 | 45% |
| 7 | Construction of Check Dam/Stop Dam | 12 | 0 | 7 | 1 | 6.68 | 5.48 | 82% |
| 8 | Plantation | 9 | 2 | 3 | 0 | 18.25 | 7.59 | 42% |
| 9 | Construction of Tank | 7 | 0 | 5 | 2 | 25.58 | 11.61 | 45% |
| 10 | Land Development | 7 | 0 | 5 | 0 | 7.58 | 5.91 | 78% |
| 11 | Farm Pond | 5 | 0 | 3 | 1 | 9.48 | 5.97 | 63% |
| 12 | Construction of Recharge Pits | 4 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| 13 | Construction of NADEP/Vermi Compost Pit | 3 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| 14 | Solid and Liquid Waste Management | 3 | 0 | 2 | 0 | 1.20 | 1.09 | 91% |
| 15 | Repair & Maint of Check Dam/Stop Dam | 2 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| 16 | Construction of Play field | 2 | 0 | 1 | 0 | 1.53 | 0.01 | 1% |
| 17 | Construction of Toilets | 2 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| 18 | Constr of Gabion | 2 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| 19 | Construction of Water Drain/Diversion Channel/Drainage/Field Channel | 2 | 0 | 2 | 0 | 0.47 | 0.47 | 99% |
| 20 | Culvert | 2 | 0 | 1 | 0 | 0.95 | 0.63 | 66% |
| 21 | Roof Water Harvesting on gov/panchayat bldg | 2 | 0 | 1 | 1 | 0.44 | 0.19 | 42% |
| 22 | Construction of Trench | 1 | 0 | 1 | 0 | 0.00 | 0.21 | 0% |
| 23 | Constr of GP Bhawan | 1 | 0 | 1 | 0 | 12.85 | 10.00 | 78% |
| 24 | Constr of Kitchen Shed | 1 | 0 | 0 | 1 | 0.16 | 0.00 | 0% |
| 25 | Construction of Crematorium | 1 | 0 | 1 | 0 | 1.80 | 1.80 | 100% |
| 26 | Community Sanitary Complex | 1 | 0 | 1 | 0 | 0.44 | 0.44 | 99% |
| Total | 366 | 59 | 210 | 17 | 321.54 | 184.01 |