| Sr. | New Work Type | Total works | Ongoing | Completed | Closed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|---|---|---|
| 1 | Rural Housing | 143 | 50 | 70 | 0 | 34.16 | 18.82 | 55% |
| 2 | Construction of Toilets | 87 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| 3 | Constr of Cement Concrete Roads | 32 | 0 | 23 | 2 | 32.09 | 26.01 | 81% |
| 4 | Land Development | 32 | 0 | 10 | 0 | 26.30 | 20.70 | 79% |
| 5 | Construction of Bund | 24 | 0 | 14 | 8 | 15.98 | 14.30 | 90% |
| 6 | Construction of Well | 21 | 0 | 11 | 4 | 36.00 | 19.27 | 54% |
| 7 | Construction of NADEP/Vermi Compost Pit | 15 | 0 | 5 | 10 | 1.67 | 0.64 | 39% |
| 8 | Farm Pond | 11 | 0 | 1 | 0 | 10.75 | 9.83 | 91% |
| 9 | Construction of Tank | 7 | 0 | 6 | 1 | 0.91 | 0.42 | 47% |
| 10 | Construction of Road and Culvert | 7 | 0 | 2 | 4 | 19.47 | 12.03 | 62% |
| 11 | Goat Shelter | 6 | 0 | 6 | 0 | 2.70 | 2.68 | 99% |
| 12 | Well Recharge | 5 | 0 | 3 | 1 | 7.58 | 0.76 | 10% |
| 13 | Plantation | 5 | 0 | 3 | 1 | 8.90 | 6.36 | 72% |
| 14 | Cattle Shed | 5 | 0 | 4 | 0 | 2.28 | 1.81 | 79% |
| 15 | Solid and Liquid Waste Management | 3 | 0 | 2 | 1 | 0.88 | 0.57 | 64% |
| 16 | Construction of Recharge Pits | 3 | 0 | 0 | 3 | 0.00 | 0.00 | 0% |
| 17 | Constr of Aganwadi | 3 | 0 | 2 | 0 | 9.90 | 4.61 | 47% |
| 18 | Construction of Water Drain/Diversion Channel/Drainage/Field Channel | 2 | 0 | 1 | 1 | 3.33 | 3.02 | 91% |
| 19 | Construction of Play field | 2 | 0 | 1 | 0 | 5.39 | 1.86 | 35% |
| 20 | Construction of Check Dam/Stop Dam | 1 | 0 | 1 | 0 | 2.40 | 2.39 | 100% |
| 21 | Construction of Crematorium | 1 | 0 | 0 | 1 | 1.92 | 0.00 | 0% |
| 22 | Constr of GP Bhawan | 1 | 0 | 1 | 0 | 12.85 | 2.85 | 22% |
| Total | 416 | 50 | 166 | 37 | 235.46 | 148.93 |