| Sr. | New Work Type | Total works | Ongoing | Completed | Closed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|---|---|---|
| 1 | Rural Housing | 79 | 33 | 31 | 0 | 18.81 | 14.45 | 77% |
| 2 | Constr of Cement Concrete Roads | 40 | 5 | 22 | 7 | 13.88 | 10.81 | 78% |
| 3 | Solid and Liquid Waste Management | 17 | 3 | 10 | 4 | 5.07 | 3.68 | 73% |
| 4 | Plantation | 14 | 1 | 8 | 3 | 32.24 | 3.56 | 11% |
| 5 | Construction of Toilets | 13 | 0 | 12 | 0 | 0.41 | 0.31 | 74% |
| 6 | Repair & maint of Pond/ Tank | 6 | 0 | 0 | 6 | 0.00 | 0.00 | 0% |
| 7 | Construction of Recharge Pits | 6 | 0 | 3 | 1 | 0.54 | 0.20 | 37% |
| 8 | Construction of Bund | 5 | 0 | 3 | 1 | 2.01 | 0.80 | 40% |
| 9 | Construction of NADEP/Vermi Compost Pit | 5 | 0 | 1 | 4 | 0.12 | 0.05 | 39% |
| 10 | Roof Water Harvesting on gov/panchayat bldg | 4 | 0 | 0 | 4 | 0.00 | 0.00 | 0% |
| 11 | Construction of Check Dam/Stop Dam | 4 | 0 | 3 | 1 | 4.80 | 0.76 | 16% |
| 12 | Construction of Trench | 4 | 0 | 2 | 2 | 1.84 | 0.79 | 43% |
| 13 | Constr of Compound wall | 3 | 0 | 3 | 0 | 7.92 | 5.40 | 68% |
| 14 | Land Development | 3 | 0 | 3 | 0 | 0.77 | 0.01 | 2% |
| 15 | Cattle Shed | 3 | 0 | 3 | 0 | 2.64 | 2.38 | 90% |
| 16 | Construction of Road and Culvert | 3 | 0 | 1 | 2 | 4.73 | 0.01 | 0% |
| 17 | Construction of Crematorium | 2 | 0 | 2 | 0 | 3.60 | 3.53 | 98% |
| 18 | Construction of Play field | 2 | 0 | 1 | 1 | 0.79 | 0.57 | 72% |
| 19 | Terracing | 2 | 0 | 2 | 0 | 1.07 | 0.70 | 65% |
| 20 | Construction of building/workshed for SHG | 2 | 0 | 0 | 2 | 2.21 | 0.00 | 0% |
| 21 | Farm Pond | 2 | 0 | 1 | 0 | 0.56 | 0.23 | 42% |
| 22 | Works for Flood Control and Protection | 1 | 0 | 1 | 0 | 2.08 | 0.65 | 31% |
| 23 | Community Sanitary Complex | 1 | 0 | 1 | 0 | 0.73 | 0.42 | 57% |
| 24 | Constr of GP Bhawan | 1 | 0 | 1 | 0 | 5.22 | 4.06 | 78% |
| 25 | Construction of Other Community Building/Assets | 1 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| 26 | Construction of Tank | 1 | 0 | 1 | 0 | 2.15 | 0.03 | 2% |
| 27 | Construction of Water Drain/Diversion Channel/Drainage/Field Channel | 1 | 0 | 1 | 0 | 0.40 | 0.32 | 80% |
| 28 | Repair & Maint of Community infrastructure | 1 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| 29 | Well Recharge | 1 | 0 | 1 | 0 | 0.26 | 0.15 | 56% |
| Total | 227 | 42 | 117 | 40 | 114.85 | 53.87 |