| Sr. | New Work Type | Total works | Ongoing | Completed | Closed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|---|---|---|
| 1 | Rural Housing | 220 | 8 | 211 | 0 | 38.28 | 36.85 | 96% |
| 2 | Construction of Toilets | 23 | 0 | 23 | 0 | 2.80 | 1.74 | 62% |
| 3 | Constr of Cement Concrete Roads | 17 | 0 | 12 | 5 | 13.43 | 5.66 | 42% |
| 4 | Construction of Trench | 16 | 1 | 11 | 2 | 74.35 | 48.87 | 66% |
| 5 | Construction of Road and Culvert | 15 | 0 | 13 | 1 | 62.11 | 64.55 | 104% |
| 6 | Farm Pond | 14 | 0 | 12 | 0 | 3.06 | 1.86 | 61% |
| 7 | Construction of Check Dam/Stop Dam | 12 | 0 | 4 | 8 | 24.64 | 24.96 | 101% |
| 8 | Land Development | 10 | 0 | 6 | 0 | 24.64 | 15.66 | 64% |
| 9 | Plantation | 8 | 2 | 3 | 3 | 18.49 | 6.67 | 36% |
| 10 | Construction of Embankment | 6 | 0 | 5 | 1 | 2.64 | 1.69 | 64% |
| 11 | Solid and Liquid Waste Management | 5 | 0 | 4 | 1 | 1.44 | 1.04 | 72% |
| 12 | Construction of NADEP/Vermi Compost Pit | 5 | 0 | 4 | 0 | 0.48 | 0.49 | 101% |
| 13 | Constr of Aganwadi | 3 | 0 | 3 | 0 | 5.98 | 5.54 | 93% |
| 14 | Construction of Tank | 3 | 0 | 2 | 1 | 9.80 | 6.92 | 71% |
| 15 | Construction of Play field | 3 | 0 | 0 | 3 | 0.00 | 0.00 | 0% |
| 16 | Culvert | 3 | 0 | 3 | 0 | 4.57 | 3.77 | 83% |
| 17 | Construction of Crematorium | 3 | 0 | 3 | 0 | 4.80 | 4.82 | 100% |
| 18 | Constr of Compound wall | 2 | 0 | 2 | 0 | 0.52 | 0.47 | 90% |
| 19 | Construction of Recharge Pits | 2 | 0 | 0 | 2 | 0.00 | 0.00 | 0% |
| 20 | Construction of Bund | 2 | 0 | 2 | 0 | 0.36 | 2.46 | 687% |
| 21 | Constr of GP Bhawan | 1 | 0 | 1 | 0 | 12.85 | 10.35 | 81% |
| 22 | Repair & Maint of Bund | 1 | 0 | 0 | 1 | 0.36 | 0.00 | 0% |
| 23 | Construction of Percolation Tank | 1 | 0 | 1 | 0 | 4.90 | 4.59 | 94% |
| 24 | Construction of Water Drain/Diversion Channel/Drainage/Field Channel | 1 | 0 | 1 | 0 | 0.36 | 0.28 | 77% |
| Total | 376 | 11 | 326 | 28 | 310.86 | 249.24 |