| Sr. | New Work Type | Total works | Ongoing | Completed | Closed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|---|---|---|
| 1 | Rural Housing | 193 | 5 | 180 | 1 | 33.48 | 30.60 | 91% |
| 2 | Construction of Bund | 58 | 0 | 26 | 18 | 17.18 | 4.54 | 26% |
| 3 | Construction of Toilets | 47 | 0 | 47 | 0 | 5.08 | 5.05 | 99% |
| 4 | Plantation | 28 | 3 | 18 | 5 | 64.85 | 6.93 | 11% |
| 5 | Repair & maint of Pond/ Tank | 24 | 0 | 1 | 0 | 0.97 | 0.84 | 87% |
| 6 | Land Development | 21 | 0 | 12 | 0 | 19.42 | 6.38 | 33% |
| 7 | Construction of Trench | 18 | 0 | 15 | 2 | 3.81 | 2.71 | 71% |
| 8 | Constr of Cement Concrete Roads | 14 | 0 | 10 | 2 | 13.16 | 6.13 | 47% |
| 9 | Construction of Road and Culvert | 12 | 0 | 7 | 3 | 44.63 | 13.15 | 30% |
| 10 | Construction of Check Dam/Stop Dam | 12 | 0 | 8 | 2 | 8.47 | 2.51 | 30% |
| 11 | Repair & Maint of Canal | 6 | 0 | 6 | 0 | 3.23 | 2.70 | 84% |
| 12 | Construction of Tank | 6 | 0 | 0 | 6 | 0.00 | 0.00 | 0% |
| 13 | Works for Flood Control and Protection | 5 | 0 | 4 | 1 | 1.37 | 0.87 | 64% |
| 14 | Construction of Recharge Pits | 5 | 0 | 5 | 0 | 0.81 | 0.75 | 92% |
| 15 | Farm Pond | 5 | 0 | 3 | 1 | 7.01 | 2.32 | 33% |
| 16 | Construction of NADEP/Vermi Compost Pit | 4 | 0 | 2 | 0 | 0.48 | 0.06 | 13% |
| 17 | Construction of Canal | 3 | 0 | 1 | 2 | 0.68 | 0.53 | 79% |
| 18 | Constr of Food Grain storage | 2 | 2 | 0 | 0 | 3.47 | 1.50 | 43% |
| 19 | Constr of Aganwadi | 2 | 0 | 1 | 0 | 1.80 | 1.71 | 95% |
| 20 | Constr of GP Bhawan | 2 | 0 | 0 | 2 | 5.79 | 0.00 | 0% |
| 21 | Terracing | 2 | 0 | 1 | 1 | 0.83 | 0.71 | 85% |
| 22 | Construction of Water Drain/Diversion Channel/Drainage/Field Channel | 2 | 0 | 1 | 0 | 0.11 | 0.11 | 99% |
| 23 | Construction of Play field | 1 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| 24 | Construction of Well | 1 | 0 | 1 | 0 | 3.38 | 1.28 | 38% |
| 25 | Deepening / Desilting of Flood Channels | 1 | 0 | 1 | 0 | 1.51 | 1.40 | 93% |
| 26 | Repair & Maint of Check Dam/Stop Dam | 1 | 1 | 0 | 0 | 2.14 | 0.04 | 2% |
| 27 | Repair & Maint of Community infrastructure | 1 | 0 | 0 | 0 | 4.00 | 0.00 | 0% |
| 28 | Constr of Compound wall | 1 | 0 | 1 | 0 | 0.45 | 0.44 | 98% |
| 29 | Solid and Liquid Waste Management | 1 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| Total | 478 | 11 | 351 | 48 | 248.10 | 93.25 |