| Sr. | New Work Type | Total works | Ongoing | Completed | Closed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|---|---|---|
| 1 | Rural Housing | 525 | 21 | 499 | 5 | 1.01 | 0.94 | 93% |
| 2 | Farm Pond | 357 | 2 | 256 | 3 | 2.26 | 1.54 | 68% |
| 3 | Land Development | 286 | 1 | 106 | 161 | 2.56 | 1.97 | 77% |
| 4 | Construction of Check Dam/Stop Dam | 273 | 0 | 254 | 12 | 2.62 | 1.83 | 70% |
| 5 | Construction of Bund | 75 | 0 | 56 | 17 | 1.05 | 0.77 | 73% |
| 6 | Construction of Toilets | 65 | 0 | 47 | 0 | 0.03 | 0.01 | 39% |
| 7 | Construction of Well | 59 | 1 | 41 | 10 | 0.95 | 0.62 | 65% |
| 8 | Plantation | 29 | 3 | 18 | 4 | 0.63 | 0.34 | 54% |
| 9 | Cattle Shed | 25 | 1 | 2 | 20 | 0.04 | 0.02 | 68% |
| 10 | Construction of Road and Culvert | 17 | 0 | 16 | 0 | 0.85 | 0.62 | 73% |
| 11 | Constr of Cement Concrete Roads | 16 | 0 | 10 | 6 | 0.24 | 0.19 | 83% |
| 12 | Repair & maint of Water Harvesting Structures | 12 | 0 | 1 | 11 | 0.09 | 0.08 | 98% |
| 13 | Well Recharge | 11 | 0 | 4 | 7 | 0.08 | 0.06 | 81% |
| 14 | Constr of Gabion | 9 | 0 | 4 | 4 | 0.78 | 0.45 | 58% |
| 15 | Construction of Trench | 8 | 0 | 7 | 1 | 0.15 | 0.12 | 81% |
| 16 | Construction of Tank | 6 | 0 | 1 | 2 | 0.08 | 0.08 | 95% |
| 17 | Deepening / Desilting of Flood Channels | 6 | 0 | 6 | 0 | 0.84 | 0.57 | 69% |
| 18 | Repair & maint of Road | 5 | 0 | 1 | 4 | 0.02 | 0.02 | 101% |
| 19 | Repair & Maint of Check Dam/Stop Dam | 4 | 0 | 2 | 2 | 0.18 | 0.16 | 88% |
| 20 | Repair & maint of Pond/ Tank | 4 | 0 | 2 | 2 | 0.32 | 0.12 | 37% |
| 21 | Construction of Water Drain/Diversion Channel/Drainage/Field Channel | 4 | 0 | 2 | 2 | 0.15 | 0.14 | 94% |
| 22 | Construction of Recharge Pits | 4 | 0 | 2 | 2 | 0.03 | 0.01 | 16% |
| 23 | Roof Water Harvesting on gov/panchayat bldg | 3 | 0 | 3 | 0 | 0.01 | 0.01 | 83% |
| 24 | Repair & Maint of Bund | 3 | 0 | 0 | 3 | 0.00 | 0.00 | 0% |
| 25 | Works for Flood Control and Protection | 2 | 0 | 2 | 0 | 0.10 | 0.10 | 100% |
| 26 | Construction of Spur | 2 | 0 | 0 | 2 | 0.00 | 0.00 | 0% |
| 27 | Construction of Embankment | 2 | 0 | 1 | 1 | 0.03 | 0.03 | 100% |
| 28 | Constr of GP Bhawan | 2 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| 29 | Goat Shelter | 2 | 0 | 0 | 2 | 0.00 | 0.00 | 0% |
| 30 | Community Sanitary Complex | 2 | 0 | 1 | 0 | 0.00 | 0.01 | 136% |
| 31 | Construction of NADEP/Vermi Compost Pit | 2 | 0 | 1 | 0 | 0.00 | 0.00 | 40% |
| 32 | Terracing | 1 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| 33 | Repair & Maint of Community infrastructure | 1 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| 34 | Construction of Crematorium | 1 | 0 | 1 | 0 | 0.02 | 0.03 | 108% |
| Total | 1,823 | 29 | 1,346 | 286 | 15.12 | 10.83 |