| Sr. | New Work Type | Total works | Ongoing | Completed | Closed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|---|---|---|
| 1 | Rural Housing | 288 | 1 | 278 | 8 | 0.55 | 0.54 | 97% |
| 2 | Farm Pond | 147 | 0 | 127 | 1 | 0.60 | 0.37 | 62% |
| 3 | Land Development | 100 | 0 | 75 | 1 | 0.59 | 0.45 | 77% |
| 4 | Construction of Bund | 80 | 1 | 55 | 12 | 1.59 | 0.81 | 51% |
| 5 | Plantation | 37 | 3 | 23 | 3 | 0.58 | 0.13 | 23% |
| 6 | Construction of Check Dam/Stop Dam | 36 | 0 | 11 | 12 | 1.38 | 1.32 | 96% |
| 7 | Solid and Liquid Waste Management | 28 | 0 | 3 | 1 | 0.02 | 0.02 | 84% |
| 8 | Constr of Cement Concrete Roads | 26 | 0 | 19 | 0 | 0.58 | 0.13 | 23% |
| 9 | Construction of Road and Culvert | 25 | 0 | 15 | 0 | 1.43 | 0.86 | 60% |
| 10 | Construction of NADEP/Vermi Compost Pit | 25 | 0 | 9 | 15 | 0.01 | 0.01 | 78% |
| 11 | Construction of Well | 20 | 2 | 11 | 0 | 0.29 | 0.20 | 71% |
| 12 | Construction of Toilets | 19 | 0 | 12 | 0 | 0.06 | 0.01 | 20% |
| 13 | Well Recharge | 15 | 1 | 9 | 2 | 0.28 | 0.02 | 8% |
| 14 | Construction of Water Drain/Diversion Channel/Drainage/Field Channel | 12 | 0 | 3 | 8 | 0.22 | 0.15 | 68% |
| 15 | Construction of Play field | 9 | 2 | 1 | 0 | 0.32 | 0.10 | 33% |
| 16 | Renovation of traditional water bodies | 7 | 0 | 6 | 0 | 2.59 | 1.93 | 75% |
| 17 | Construction of Recharge Pits | 6 | 0 | 3 | 1 | 0.02 | 0.02 | 77% |
| 18 | Community Sanitary Complex | 6 | 1 | 1 | 0 | 0.01 | 0.01 | 89% |
| 19 | Construction of Tank | 5 | 0 | 1 | 0 | 0.03 | 0.02 | 54% |
| 20 | Cattle Shed | 5 | 0 | 1 | 0 | 0.04 | 0.01 | 18% |
| 21 | Constr of Gabion | 5 | 0 | 3 | 2 | 0.12 | 0.12 | 95% |
| 22 | Construction of Trench | 5 | 0 | 1 | 2 | 0.23 | 0.04 | 19% |
| 23 | Repair & maint of Pond/ Tank | 4 | 0 | 2 | 1 | 0.05 | 0.03 | 71% |
| 24 | Repair & maint of Water Harvesting Structures | 4 | 0 | 3 | 1 | 0.03 | 0.03 | 91% |
| 25 | Construction of Canal | 4 | 0 | 3 | 1 | 0.09 | 0.08 | 84% |
| 26 | Repair & Maint of Bund | 3 | 0 | 1 | 1 | 0.02 | 0.01 | 68% |
| 27 | Construction of Crematorium | 3 | 0 | 1 | 1 | 0.04 | 0.02 | 46% |
| 28 | Construction of Percolation Tank | 2 | 0 | 1 | 0 | 0.02 | 0.02 | 77% |
| 29 | Constr of GP Bhawan | 1 | 0 | 1 | 0 | 0.13 | 0.10 | 75% |
| 30 | Boulder Check/Gully Plug | 1 | 0 | 1 | 0 | 0.03 | 0.02 | 92% |
| 31 | Construction of Spur | 1 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| 32 | Lift Irrigation | 1 | 0 | 1 | 0 | 0.34 | 0.29 | 85% |
| 33 | Construction of Other Community Building/Assets | 1 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| 34 | Deepening / Desilting of Flood Channels | 1 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| Total | 932 | 11 | 681 | 74 | 12.27 | 7.85 |