| Sr. | New Work Type | Total works | Ongoing | Completed | Closed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|---|---|---|
| 1 | Solid and Liquid Waste Management | 11 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| 2 | Constr of Compound wall | 6 | 0 | 0 | 0 | 7.35 | 0.00 | 0% |
| 3 | Construction of Trench | 5 | 1 | 0 | 0 | 22.81 | 1.48 | 7% |
| 4 | Construction of Check Dam/Stop Dam | 5 | 0 | 0 | 0 | 9.16 | 0.00 | 0% |
| 5 | Construction of Well | 4 | 3 | 0 | 0 | 8.85 | 0.00 | 0% |
| 6 | Plantation | 4 | 3 | 0 | 0 | 8.65 | 0.00 | 0% |
| 7 | Farm Pond | 3 | 1 | 0 | 0 | 3.83 | 0.00 | 0% |
| 8 | Construction of Canal | 2 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| 9 | Construction of Recharge Pits | 2 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| 10 | Constr of Cement Concrete Roads | 1 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| 11 | Construction of Road and Culvert | 1 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| 12 | Repair & maint of Pond/ Tank | 1 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| 13 | Rural Housing | 1 | 1 | 0 | 0 | 0.29 | 0.03 | 11% |
| 14 | Construction of Crematorium | 1 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| Total | 47 | 9 | 0 | 0 | 60.93 | 1.51 |