| Sr. | New Work Type | Total works | Ongoing | Completed | Closed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|---|---|---|
| 1 | Rural Housing | 206 | 0 | 200 | 0 | 0.39 | 0.35 | 90% |
| 2 | Land Development | 95 | 0 | 89 | 0 | 1.09 | 0.63 | 58% |
| 3 | Farm Pond | 85 | 0 | 59 | 0 | 2.08 | 1.18 | 57% |
| 4 | Construction of Check Dam/Stop Dam | 82 | 0 | 39 | 18 | 4.62 | 4.23 | 92% |
| 5 | Construction of Well | 78 | 7 | 28 | 1 | 1.53 | 0.80 | 52% |
| 6 | Construction of Bund | 70 | 1 | 33 | 3 | 2.29 | 2.03 | 89% |
| 7 | Construction of Percolation Tank | 59 | 1 | 40 | 14 | 6.46 | 5.95 | 92% |
| 8 | Construction of NADEP/Vermi Compost Pit | 53 | 0 | 39 | 6 | 0.15 | 0.07 | 48% |
| 9 | Plantation | 40 | 5 | 17 | 0 | 0.69 | 0.16 | 23% |
| 10 | Boulder Check/Gully Plug | 40 | 0 | 31 | 5 | 0.94 | 0.32 | 34% |
| 11 | Construction of Toilets | 31 | 0 | 29 | 1 | 0.02 | 0.01 | 63% |
| 12 | Constr of Cement Concrete Roads | 20 | 1 | 12 | 0 | 0.68 | 0.49 | 72% |
| 13 | Cattle Shed | 20 | 0 | 19 | 0 | 0.13 | 0.12 | 91% |
| 14 | Well Recharge | 14 | 0 | 8 | 1 | 0.15 | 0.11 | 77% |
| 15 | Construction of Road and Culvert | 14 | 0 | 7 | 1 | 0.89 | 0.37 | 41% |
| 16 | Construction of Tank | 13 | 7 | 3 | 0 | 1.20 | 0.88 | 73% |
| 17 | Construction of Trench | 10 | 0 | 8 | 0 | 0.48 | 0.41 | 86% |
| 18 | Construction of Water Drain/Diversion Channel/Drainage/Field Channel | 7 | 0 | 3 | 1 | 0.26 | 0.07 | 28% |
| 19 | Renovation of traditional water bodies | 6 | 0 | 6 | 0 | 0.09 | 0.04 | 45% |
| 20 | Terracing | 6 | 0 | 6 | 0 | 0.06 | 0.04 | 71% |
| 21 | Goat Shelter | 5 | 0 | 5 | 0 | 0.03 | 0.02 | 82% |
| 22 | Constr of GP Bhawan | 5 | 0 | 1 | 0 | 0.10 | 0.10 | 98% |
| 23 | Solid and Liquid Waste Management | 5 | 0 | 2 | 1 | 0.02 | 0.00 | 11% |
| 24 | Repair & maint of Percolation Tank | 3 | 0 | 3 | 0 | 0.45 | 0.43 | 96% |
| 25 | Construction of Recharge Pits | 3 | 0 | 1 | 2 | 0.00 | 0.00 | 48% |
| 26 | Construction of Play field | 2 | 0 | 2 | 0 | 0.06 | 0.04 | 68% |
| 27 | Underground Dyke for Ground Water Recharge | 2 | 0 | 2 | 0 | 0.10 | 0.14 | 140% |
| 28 | Constr of Kitchen Shed | 2 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| 29 | Repair & maint of Water Harvesting Structures | 2 | 0 | 0 | 1 | 0.02 | 0.00 | 0% |
| 30 | Community Sanitary Complex | 1 | 0 | 1 | 0 | 0.00 | 0.00 | 85% |
| 31 | Construction of Spur | 1 | 0 | 1 | 0 | 0.06 | 0.05 | 79% |
| 32 | Construction of Fish Drying Infrastructure | 1 | 0 | 0 | 0 | 0.01 | 0.00 | 0% |
| 33 | Repair & Maint of Bund | 1 | 0 | 0 | 0 | 0.04 | 0.00 | 0% |
| 34 | Repair & Maint of Check Dam/Stop Dam | 1 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| 35 | Repair & maint of Pond/ Tank | 1 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| Total | 984 | 22 | 694 | 58 | 25.11 | 19.05 |