| Sr. | New Work Type | Total works | Ongoing | Completed | Closed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|---|---|---|
| 1 | Rural Housing | 193 | 22 | 142 | 1 | 40.60 | 30.96 | 76% |
| 2 | Plantation | 41 | 11 | 20 | 1 | 60.93 | 21.76 | 36% |
| 3 | Construction of NADEP/Vermi Compost Pit | 27 | 0 | 11 | 16 | 3.88 | 1.64 | 42% |
| 4 | Constr of Cement Concrete Roads | 27 | 0 | 17 | 6 | 29.02 | 11.77 | 41% |
| 5 | Construction of Well | 23 | 2 | 15 | 4 | 63.79 | 42.11 | 66% |
| 6 | Construction of Recharge Pits | 14 | 0 | 13 | 1 | 2.50 | 2.34 | 94% |
| 7 | Well Recharge | 11 | 0 | 9 | 0 | 8.88 | 8.31 | 94% |
| 8 | Construction of Check Dam/Stop Dam | 8 | 0 | 4 | 3 | 16.30 | 12.97 | 80% |
| 9 | Works for Flood Control and Protection | 8 | 1 | 6 | 1 | 38.57 | 22.56 | 59% |
| 10 | Farm Pond | 8 | 0 | 5 | 1 | 20.36 | 11.23 | 55% |
| 11 | Construction of Road and Culvert | 7 | 1 | 6 | 0 | 82.84 | 71.23 | 86% |
| 12 | Repair & Maint of Check Dam/Stop Dam | 7 | 0 | 4 | 3 | 6.14 | 4.90 | 80% |
| 13 | Construction of Percolation Tank | 7 | 0 | 2 | 3 | 8.60 | 4.25 | 50% |
| 14 | Construction of Trench | 6 | 0 | 5 | 1 | 23.50 | 16.64 | 71% |
| 15 | Repair & maint of Pond/ Tank | 6 | 0 | 5 | 1 | 26.66 | 20.89 | 78% |
| 16 | Community Sanitary Complex | 5 | 0 | 4 | 1 | 2.19 | 1.65 | 76% |
| 17 | Cattle Shed | 4 | 0 | 1 | 0 | 39.46 | 34.21 | 87% |
| 18 | Construction of Crematorium | 3 | 0 | 3 | 0 | 7.57 | 6.41 | 85% |
| 19 | Solid and Liquid Waste Management | 3 | 0 | 0 | 3 | 0.16 | 0.00 | 0% |
| 20 | Renovation of traditional water bodies | 2 | 0 | 1 | 0 | 1.50 | 0.67 | 45% |
| 21 | Land Development | 2 | 1 | 0 | 0 | 11.95 | 4.51 | 38% |
| 22 | Roof Water Harvesting on gov/panchayat bldg | 1 | 0 | 0 | 1 | 0.25 | 0.00 | 0% |
| 23 | Constr of Kitchen Shed | 1 | 0 | 0 | 1 | 0.16 | 0.00 | 0% |
| 24 | Constr of GP Bhawan | 1 | 0 | 1 | 0 | 12.85 | 9.60 | 75% |
| 25 | Grass Land Development | 1 | 0 | 0 | 0 | 3.65 | 3.26 | 89% |
| 26 | Construction of Tank | 1 | 0 | 0 | 0 | 1.33 | 1.12 | 85% |
| 27 | Construction of building/workshed for SHG | 1 | 0 | 1 | 0 | 1.80 | 1.54 | 86% |
| 28 | Construction of Play field | 1 | 0 | 1 | 0 | 3.53 | 2.96 | 84% |
| 29 | Repair & maint of Road | 1 | 0 | 0 | 0 | 9.25 | 7.90 | 85% |
| Total | 420 | 38 | 276 | 48 | 528.21 | 357.40 |