| Sr. | New Work Type | Total works | Ongoing | Completed | Closed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|---|---|---|
| 1 | Rural Housing | 222 | 0 | 214 | 1 | 0.39 | 0.37 | 95% |
| 2 | Construction of Well | 74 | 6 | 24 | 20 | 0.84 | 0.30 | 36% |
| 3 | Construction of Bund | 30 | 0 | 0 | 30 | 0.00 | 0.00 | 0% |
| 4 | Construction of Check Dam/Stop Dam | 29 | 1 | 13 | 10 | 0.50 | 0.17 | 34% |
| 5 | Construction of Road and Culvert | 29 | 0 | 21 | 0 | 1.35 | 0.75 | 56% |
| 6 | Farm Pond | 26 | 0 | 0 | 10 | 0.27 | 0.11 | 41% |
| 7 | Constr of Cement Concrete Roads | 16 | 0 | 7 | 4 | 0.15 | 0.10 | 62% |
| 8 | Well Recharge | 14 | 0 | 0 | 0 | 0.03 | 0.03 | 88% |
| 9 | Land Development | 14 | 0 | 0 | 1 | 0.03 | 0.00 | 0% |
| 10 | Plantation | 14 | 1 | 0 | 6 | 0.27 | 0.01 | 3% |
| 11 | Cattle Shed | 11 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| 12 | Goat Shelter | 10 | 1 | 0 | 0 | 0.01 | 0.00 | 9% |
| 13 | Construction of Percolation Tank | 9 | 1 | 0 | 5 | 0.39 | 0.10 | 26% |
| 14 | Construction of NADEP/Vermi Compost Pit | 8 | 0 | 0 | 8 | 0.00 | 0.00 | 0% |
| 15 | Construction of Tank | 4 | 0 | 0 | 3 | 0.25 | 0.00 | 0% |
| 16 | Repair & maint of Pond/ Tank | 4 | 0 | 0 | 3 | 0.10 | 0.03 | 31% |
| 17 | Solid and Liquid Waste Management | 3 | 0 | 0 | 3 | 0.00 | 0.00 | 0% |
| 18 | Construction of Recharge Pits | 2 | 0 | 1 | 1 | 0.12 | 0.04 | 35% |
| 19 | Constr of Aganwadi | 2 | 0 | 1 | 1 | 0.04 | 0.02 | 53% |
| 20 | Construction of Fish Drying Infrastructure | 2 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| 21 | Terracing | 1 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| 22 | Construction of building/workshed for SHG | 1 | 1 | 0 | 0 | 0.03 | 0.03 | 84% |
| 23 | Constr of Gabion | 1 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| 24 | Construction of Play field | 1 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| 25 | Repair & Maint of Community infrastructure | 1 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| Total | 528 | 11 | 281 | 107 | 4.76 | 2.05 |