MGNREGA Works Dashboard
MGNREGA VBGRAMG MGNREGA + VBGRAMG
Admin login

Overall

Rollup last refreshed: 2026-09-21 06:52:32.583578 · figures are real, from vg_work_summary_rollup
to
to
Reset filters
Total works
17
All statuses · all years
Approved
6
35.3% of total
Ongoing
7
41.2% of total
Physically Completed
4
23.5% of total
Sanctioned
₹38.05 L
Pure scheme basis
Expenditure %
5.4%
₹2.04 L of ₹38.05 L

Detailed breakdown (All amounts in ₹ Lakh)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Total works Ongoing Completed Closed Sanctioned Expenditure Exp. %
1 Construction of Well 4 4 0 0 11.68 0.00
0%
2 Constr of Cement Concrete Roads 4 0 0 0 1.34 0.00
0%
3 Cattle Shed 3 0 0 0 3.90 0.00
0%
4 Plantation 2 2 0 0 3.91 0.22
6%
5 Construction of Water Drain/Diversion Channel/Drainage/Field Channel 2 0 0 0 1.43 0.24
17%
6 Construction of Trench 1 1 0 0 3.96 1.59
40%
7 Constr of Food Grain storage 1 0 0 0 11.82 0.00
0%
Total 17 7 0 0 38.05 2.04
All 7 rows (zero-value rows hidden) ⇩ Export to Excel