Total works
9
All statuses · all years
Approved
5
55.6% of total
New
1
11.1% of total
Ongoing
3
33.3% of total
Sanctioned
₹15.49 L
Pure scheme basis
Expenditure %
8.1%
₹1.25 L of ₹15.49 L

Detailed breakdown (All amounts in ₹ Lakh)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Total works Ongoing Completed Closed Sanctioned Expenditure Exp. %
1 Construction of Trench 3 1 0 0 5.96 1.25
21%
2 Rural Housing 2 0 0 0 0.54 0.00
0%
3 Constr of Aganwadi 1 1 0 0 5.00 0.00
0%
4 Construction of Crematorium 1 0 0 0 3.47 0.00
0%
5 Plantation 1 0 0 0 0.00 0.00
0%
6 Poultry Shelter 1 1 0 0 0.52 0.00
0%
Total 9 3 0 0 15.49 1.25
All 6 rows (zero-value rows hidden) ⇩ Export to Excel