| Sr. | New Work Type | Total works | Ongoing | Completed | Closed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|---|---|---|
| 1 | Rural Housing | 306 | 5 | 293 | 1 | 0.54 | 0.51 | 94% |
| 2 | Construction of Bund | 40 | 0 | 28 | 10 | 0.19 | 0.07 | 39% |
| 3 | Construction of Road and Culvert | 25 | 0 | 10 | 8 | 1.39 | 0.61 | 44% |
| 4 | Constr of Cement Concrete Roads | 23 | 0 | 14 | 6 | 0.12 | 0.11 | 93% |
| 5 | Solid and Liquid Waste Management | 22 | 0 | 8 | 14 | 0.01 | 0.00 | 25% |
| 6 | Construction of Recharge Pits | 18 | 0 | 7 | 8 | 0.02 | 0.00 | 7% |
| 7 | Construction of Trench | 17 | 0 | 14 | 2 | 1.11 | 0.89 | 80% |
| 8 | Farm Pond | 17 | 0 | 16 | 0 | 0.04 | 0.04 | 90% |
| 9 | Plantation | 16 | 0 | 7 | 0 | 0.52 | 0.22 | 42% |
| 10 | Cattle Shed | 13 | 0 | 13 | 0 | 0.12 | 0.00 | 1% |
| 11 | Land Development | 7 | 0 | 3 | 0 | 0.21 | 0.18 | 82% |
| 12 | Construction of Check Dam/Stop Dam | 5 | 0 | 4 | 0 | 0.48 | 0.20 | 41% |
| 13 | Renovation of traditional water bodies | 5 | 0 | 3 | 1 | 0.27 | 0.12 | 43% |
| 14 | Construction of NADEP/Vermi Compost Pit | 5 | 0 | 4 | 1 | 0.01 | 0.00 | 70% |
| 15 | Construction of Water Drain/Diversion Channel/Drainage/Field Channel | 4 | 0 | 2 | 0 | 0.29 | 0.24 | 85% |
| 16 | Constr of Gabion | 4 | 0 | 2 | 0 | 0.51 | 0.45 | 89% |
| 17 | Construction of Crematorium | 3 | 0 | 2 | 0 | 0.04 | 0.02 | 42% |
| 18 | Construction of Well | 3 | 0 | 3 | 0 | 0.02 | 0.03 | 154% |
| 19 | Terracing | 2 | 0 | 1 | 0 | 0.25 | 0.10 | 41% |
| 20 | Constr of Aganwadi | 2 | 0 | 1 | 1 | 0.16 | 0.02 | 11% |
| 21 | Construction of Embankment | 2 | 0 | 0 | 1 | 0.28 | 0.01 | 5% |
| 22 | Construction of Play field | 2 | 0 | 2 | 0 | 0.13 | 0.07 | 55% |
| 23 | Repair & maint of Pond/ Tank | 2 | 0 | 1 | 1 | 0.05 | 0.04 | 78% |
| 24 | Boulder Check/Gully Plug | 2 | 0 | 2 | 0 | 0.28 | 0.26 | 94% |
| 25 | Constr of Food Grain storage | 1 | 0 | 0 | 1 | 0.10 | 0.00 | 0% |
| 26 | Community Sanitary Complex | 1 | 0 | 1 | 0 | 0.00 | 0.00 | 84% |
| 27 | Constr of Compound wall | 1 | 0 | 1 | 0 | 0.01 | 0.01 | 72% |
| 28 | Construction of Tank | 1 | 0 | 0 | 0 | 0.14 | 0.01 | 4% |
| 29 | Constr of Kitchen Shed | 1 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| Total | 550 | 5 | 442 | 56 | 7.30 | 4.22 |