Monitor — Ongoing Works
Rollup last refreshed: 2026-09-15 07:04:12.299416
Works ongoing
5
Sanctioned (pure scheme)
₹4.58 L
Expenditure since inception
₹1.78 L
Balance cost (unspent)
₹2.80 L
Wage ₹2.44 L · Material ₹35,993
Expenditure trend
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
Slowest spending this week — worth a look
- RAJGARH — SARANGPUR−₹97.29 L
Mandays trend
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Well Recharge
1 works
₹1.93 L sanctioned
₹38,575 spent (20%)
02
Constr of Aganwadi
1 works
₹1.80 L sanctioned
₹1.28 L spent (71%)
03
Rural Housing
2 works
₹54,000 sanctioned
₹11,001 spent (20%)
04
Roof Water Harvesting on gov/panchayat bldg
1 works
₹30,497 sanctioned
₹300 spent (1%)
05
Construction of Play field
0 works
₹0 sanctioned
₹0 spent (0%)
06
Construction of Recharge Pits
0 works
₹0 sanctioned
₹0 spent (0%)
07
Construction of Road and Culvert
0 works
₹0 sanctioned
₹0 spent (0%)
08
Construction of Tank
0 works
₹0 sanctioned
₹0 spent (0%)
09
Community Sanitary Complex
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Trench
0 works
₹0 sanctioned
₹0 spent (0%)