Monitor — Ongoing Works
Rollup last refreshed: 2026-09-16 11:30:19.52397
Works ongoing
11,278
Sanctioned (pure scheme)
₹98.50 Cr
Expenditure since inception
₹37.08 Cr
Balance cost (unspent)
₹61.42 Cr
Wage ₹37.18 Cr · Material ₹24.24 Cr
Expenditure trend
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
Slowest spending this week — worth a look
- RAJGARH — SARANGPUR−₹1.02 Cr
Mandays trend
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Plantation
997 works
₹26.65 Cr sanctioned
₹6.64 Cr spent (25%)
02
Rural Housing
8,938 works
₹24.13 Cr sanctioned
₹8.68 Cr spent (36%)
03
Construction of Road and Culvert
123 works
₹14.15 Cr sanctioned
₹7.41 Cr spent (52%)
04
Construction of Tank
44 works
₹4.33 Cr sanctioned
₹2.27 Cr spent (53%)
05
Cattle Shed
40 works
₹4.09 Cr sanctioned
₹3.45 Cr spent (84%)
06
Construction of Check Dam/Stop Dam
51 works
₹3.12 Cr sanctioned
₹34.59 L spent (11%)
07
Constr of GP Bhawan
37 works
₹2.41 Cr sanctioned
₹1.62 Cr spent (67%)
08
Construction of Well
81 works
₹2.34 Cr sanctioned
₹1.02 Cr spent (43%)
09
Farm Pond
74 works
₹1.98 Cr sanctioned
₹36.74 L spent (19%)
10
Nursery Development
6 works
₹1.73 Cr sanctioned
₹13.40 L spent (8%)