Monitor — Ongoing Works
Rollup last refreshed: 2026-10-05 07:04:05.423839
Works ongoing
12,605
Sanctioned (pure scheme)
₹119.66 Cr
Expenditure since inception
₹50.04 Cr
Balance cost (unspent)
₹69.63 Cr
Wage ₹40.33 Cr · Material ₹29.29 Cr
Expenditure trend
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
Slowest spending this week — worth a look
Mandays trend
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Plantation
1,150 works
₹34.50 Cr sanctioned
₹17.96 Cr spent (52%)
02
Rural Housing
9,325 works
₹25.18 Cr sanctioned
₹10.22 Cr spent (41%)
03
Construction of Well
845 works
₹21.10 Cr sanctioned
₹9.99 Cr spent (47%)
04
Construction of Check Dam/Stop Dam
169 works
₹7.74 Cr sanctioned
₹1.43 Cr spent (18%)
05
Construction of Trench
147 works
₹5.96 Cr sanctioned
₹1.01 Cr spent (17%)
06
Cattle Shed
242 works
₹5.66 Cr sanctioned
₹3.57 Cr spent (63%)
07
Farm Pond
117 works
₹2.77 Cr sanctioned
₹47.49 L spent (17%)
08
Construction of Tank
55 works
₹2.43 Cr sanctioned
₹83.56 L spent (34%)
09
Construction of Percolation Tank
20 works
₹1.76 Cr sanctioned
₹31.22 L spent (18%)
10
Construction of Road and Culvert
14 works
₹1.54 Cr sanctioned
₹70.10 L spent (45%)