Monitor — Ongoing Works
Rollup last refreshed: 2026-09-21 07:03:55.111558
Works ongoing
5
Sanctioned (pure scheme)
₹20.69 L
Expenditure since inception
₹1.61 L
Balance cost (unspent)
₹19.08 L
Wage ₹11.82 L · Material ₹7.26 L
Expenditure trend
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
Slowest spending this week — worth a look
- DEWAS — TONK KHURD−₹6,000
Mandays trend
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Plantation
1 works
₹9.55 L sanctioned
₹600 spent (0%)
02
Construction of Tank
1 works
₹7.18 L sanctioned
₹34,686 spent (5%)
03
Construction of Well
1 works
₹2.30 L sanctioned
₹10,320 spent (4%)
04
Construction of Check Dam/Stop Dam
2 works
₹1.66 L sanctioned
₹1.15 L spent (69%)
05
Constr of Gabion
0 works
₹0 sanctioned
₹0 spent (0%)
06
Construction of Bund
0 works
₹0 sanctioned
₹0 spent (0%)
07
Construction of Crematorium
0 works
₹0 sanctioned
₹0 spent (0%)
08
Construction of NADEP/Vermi Compost Pit
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Recharge Pits
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Road and Culvert
0 works
₹0 sanctioned
₹0 spent (0%)