Monitor — Ongoing Works
Rollup last refreshed: 2026-09-19 06:51:50.312319
Works ongoing
4,139
Sanctioned (pure scheme)
₹102.56 Cr
Expenditure since inception
₹1.15 Cr
Balance cost (unspent)
₹101.41 Cr
Wage ₹41.90 Cr · Material ₹59.51 Cr
Expenditure trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
Slowest spending this week — worth a look
- RAJGARH — SARANGPUR−₹99.49 L
Mandays trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Plantation
858 works
₹22.09 Cr sanctioned
₹47.41 L spent (2%)
02
Construction of Well
477 works
₹16.11 Cr sanctioned
₹13.31 L spent (1%)
03
Construction of Road and Culvert
67 works
₹11.91 Cr sanctioned
₹10.98 L spent (1%)
04
Construction of Check Dam/Stop Dam
81 works
₹6.31 Cr sanctioned
₹72,819 spent (0%)
05
Farm Pond
162 works
₹5.12 Cr sanctioned
₹46,963 spent (0%)
06
Cattle Shed
268 works
₹4.78 Cr sanctioned
₹7.55 L spent (2%)
07
Rural Housing
1,622 works
₹4.63 Cr sanctioned
₹25.82 L spent (6%)
08
Construction of Tank
32 works
₹4.31 Cr sanctioned
₹1.38 L spent (0%)
09
Constr of Cement Concrete Roads
116 works
₹3.49 Cr sanctioned
₹74,276 spent (0%)
10
Constr of Compound wall
25 works
₹3.37 Cr sanctioned
₹0 spent (0%)