Monitor — Ongoing Works
Rollup last refreshed: 2026-09-14 07:02:51.614626
Works ongoing
3,475
Sanctioned (pure scheme)
₹74.47 Cr
Expenditure since inception
₹27.14 Cr
Balance cost (unspent)
₹47.33 Cr
Wage ₹23.85 Cr · Material ₹23.47 Cr
Expenditure trend
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
Slowest spending this week — worth a look
Mandays trend
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Plantation
614 works
₹16.73 Cr sanctioned
₹4.65 Cr spent (28%)
02
Construction of Tank
57 works
₹7.38 Cr sanctioned
₹4.27 Cr spent (58%)
03
Construction of Well
145 works
₹4.62 Cr sanctioned
₹1.87 Cr spent (40%)
04
Constr of Cement Concrete Roads
111 works
₹4.45 Cr sanctioned
₹77.22 L spent (17%)
05
Construction of Trench
52 works
₹4.13 Cr sanctioned
₹1.14 Cr spent (28%)
06
Repair & maint of Pond/ Tank
59 works
₹4.09 Cr sanctioned
₹1.98 Cr spent (49%)
07
Rural Housing
1,509 works
₹4.08 Cr sanctioned
₹1.71 Cr spent (42%)
08
Construction of Bund
79 works
₹3.65 Cr sanctioned
₹1.38 Cr spent (38%)
09
Construction of Check Dam/Stop Dam
28 works
₹3.16 Cr sanctioned
₹1.83 Cr spent (58%)
10
Construction of Road and Culvert
28 works
₹2.59 Cr sanctioned
₹1.56 Cr spent (60%)