MGNREGA Works Dashboard
MGNREGA VBGRAMG MGNREGA + VBGRAMG
Admin login

Monitor — Ongoing Works

Rollup last refreshed: 2026-09-28 07:03:45.697721
to
Reset filters
Works ongoing
29
Sanctioned (pure scheme)
₹29.28 L
Expenditure since inception
₹11.42 L
Balance cost (unspent)
₹17.86 L
Wage ₹9.69 L · Material ₹8.17 L
Expenditure trend
₹3.09 Cr
This Week
₹23.43 Cr
Last Week
▼ 86.8% vs last week
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
Slowest spending this week — worth a look
  • REWA — SIRMOUR−₹20,500
Mandays trend
1,15,804
This Week
11,32,881
Last Week
▼ 89.8%
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
Lowest mandays this week — worth a look
  • SIDHI — KUSMI-49

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Plantation
8 works
₹14.21 L sanctioned
₹3.71 L spent (26%)
02
Rural Housing
17 works
₹4.59 L sanctioned
₹2.86 L spent (62%)
03
Farm Pond
1 works
₹4.54 L sanctioned
₹67,100 spent (15%)
04
Terracing
1 works
₹3.68 L sanctioned
₹3.08 L spent (84%)
05
Community Sanitary Complex
1 works
₹1.58 L sanctioned
₹42,180 spent (27%)
06
Construction of Road and Culvert
1 works
₹68,500 sanctioned
₹67,206 spent (98%)
07
Construction of Bund
0 works
₹0 sanctioned
₹0 spent (0%)
08
Construction of Canal
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Check Dam/Stop Dam
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Crematorium
0 works
₹0 sanctioned
₹0 spent (0%)

Detailed breakdown (All amounts in ₹ Lakh)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Ongoing works Sanctioned Expenditure Balance cost Exp. %
1 Rural Housing 17 4.59 2.86 1.73
62%
2 Plantation 8 14.21 3.71 10.50
26%
3 Construction of Road and Culvert 1 0.69 0.67 0.01
98%
4 Community Sanitary Complex 1 1.58 0.42 1.16
27%
5 Terracing 1 3.68 3.08 0.60
84%
6 Farm Pond 1 4.54 0.67 3.86
15%
Total 29 29.28 11.42 17.86
All 6 rows (zero-value rows hidden) ⇩ Export to Excel