MGNREGA Works Dashboard
MGNREGA VBGRAMG MGNREGA + VBGRAMG
Admin login

Monitor — Ongoing Works

Rollup last refreshed: 2026-09-30 07:03:04.702571
to
Reset filters
Works ongoing
35
Sanctioned (pure scheme)
₹42.12 L
Expenditure since inception
₹8.61 L
Balance cost (unspent)
₹33.51 L
Wage ₹20.39 L · Material ₹13.12 L
Expenditure trend
₹13.75 Cr
This Week
₹23.43 Cr
Last Week
▼ 41.3% vs last week
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
Slowest spending this week — worth a look
  • UJJAIN — TARANA−₹12.42 L
Mandays trend
5,19,790
This Week
11,32,881
Last Week
▼ 54.1%
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
Lowest mandays this week — worth a look
  • MORENA — PAHADGARH0

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Well
4 works
₹13.04 L sanctioned
₹5.16 L spent (40%)
02
Rural Housing
22 works
₹5.94 L sanctioned
₹2.41 L spent (41%)
03
Well Recharge
1 works
₹4.45 L sanctioned
₹33,930 spent (8%)
04
Construction of Bund
2 works
₹4.11 L sanctioned
₹15,537 spent (4%)
05
Construction of Tank
1 works
₹4.00 L sanctioned
₹0 spent (0%)
06
Farm Pond
1 works
₹3.97 L sanctioned
₹2,088 spent (1%)
07
Repair & maint of Pond/ Tank
1 works
₹3.33 L sanctioned
₹8,369 spent (3%)
08
Construction of Check Dam/Stop Dam
1 works
₹2.33 L sanctioned
₹42,768 spent (18%)
09
Constr of Cement Concrete Roads
2 works
₹95,000 sanctioned
₹1,326 spent (1%)
10
Construction of Recharge Pits
0 works
₹0 sanctioned
₹0 spent (0%)

Detailed breakdown (All amounts in ₹ Lakh)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Ongoing works Sanctioned Expenditure Balance cost Exp. %
1 Rural Housing 22 5.94 2.41 3.53
41%
2 Construction of Well 4 13.04 5.16 7.88
40%
3 Constr of Cement Concrete Roads 2 0.95 0.01 0.94
1%
4 Construction of Bund 2 4.11 0.16 3.95
4%
5 Construction of Check Dam/Stop Dam 1 2.33 0.43 1.90
18%
6 Well Recharge 1 4.45 0.34 4.11
8%
7 Repair & maint of Pond/ Tank 1 3.33 0.08 3.24
3%
8 Farm Pond 1 3.97 0.02 3.95
1%
9 Construction of Tank 1 4.00 0.00 4.00
0%
Total 35 42.12 8.61 33.51