Monitor — Ongoing Works
Rollup last refreshed: 2026-08-18 08:40:27.466697
Works ongoing
7,182
Sanctioned (pure scheme)
₹687.22 Cr
Expenditure since inception
₹390.46 Cr
Balance cost (unspent)
₹296.76 Cr
Wage ₹194.81 Cr · Material ₹101.95 Cr
Expenditure trend
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
Slowest spending this week — worth a look
Mandays trend
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Tank
1,660 works
₹245.25 Cr sanctioned
₹145.94 Cr spent (60%)
02
Construction of Bund
1,257 works
₹171.62 Cr sanctioned
₹101.08 Cr spent (59%)
03
Plantation
1,155 works
₹50.63 Cr sanctioned
₹16.18 Cr spent (32%)
04
Works for Flood Control and Protection
376 works
₹46.50 Cr sanctioned
₹27.16 Cr spent (58%)
05
Construction of Check Dam/Stop Dam
273 works
₹38.01 Cr sanctioned
₹20.01 Cr spent (53%)
06
Construction of Road and Culvert
187 works
₹31.99 Cr sanctioned
₹21.51 Cr spent (67%)
07
Farm Pond
470 works
₹16.38 Cr sanctioned
₹6.82 Cr spent (42%)
08
Land Development
110 works
₹13.25 Cr sanctioned
₹7.42 Cr spent (56%)
09
Constr of Cement Concrete Roads
215 works
₹11.25 Cr sanctioned
₹8.54 Cr spent (76%)
10
Construction of Percolation Tank
42 works
₹6.34 Cr sanctioned
₹3.57 Cr spent (56%)