Monitor — Ongoing Works
Rollup last refreshed: 2026-08-26 17:54:53.293656
Works ongoing
7,069
Sanctioned (pure scheme)
₹686.31 Cr
Expenditure since inception
₹394.53 Cr
Balance cost (unspent)
₹291.78 Cr
Wage ₹191.15 Cr · Material ₹100.62 Cr
Expenditure trend
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
Slowest spending this week — worth a look
Mandays trend
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Tank
1,656 works
₹245.19 Cr sanctioned
₹146.06 Cr spent (60%)
02
Construction of Bund
1,284 works
₹174.26 Cr sanctioned
₹103.84 Cr spent (60%)
03
Plantation
1,136 works
₹50.09 Cr sanctioned
₹16.23 Cr spent (32%)
04
Works for Flood Control and Protection
378 works
₹46.95 Cr sanctioned
₹27.96 Cr spent (60%)
05
Construction of Check Dam/Stop Dam
266 works
₹37.08 Cr sanctioned
₹20.15 Cr spent (54%)
06
Construction of Road and Culvert
188 works
₹32.24 Cr sanctioned
₹21.65 Cr spent (67%)
07
Farm Pond
418 works
₹14.55 Cr sanctioned
₹6.86 Cr spent (47%)
08
Land Development
107 works
₹13.22 Cr sanctioned
₹7.44 Cr spent (56%)
09
Constr of Cement Concrete Roads
211 works
₹11.21 Cr sanctioned
₹8.54 Cr spent (76%)
10
Construction of Percolation Tank
42 works
₹6.34 Cr sanctioned
₹3.57 Cr spent (56%)