Monitor — Ongoing Works
Rollup last refreshed: 2026-09-14 07:02:51.614626
Works ongoing
9,254
Sanctioned (pure scheme)
₹122.34 Cr
Expenditure since inception
₹56.61 Cr
Balance cost (unspent)
₹65.73 Cr
Wage ₹42.07 Cr · Material ₹23.65 Cr
Expenditure trend
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
Slowest spending this week — worth a look
Mandays trend
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Plantation
696 works
₹18.52 Cr sanctioned
₹5.51 Cr spent (30%)
02
Construction of Tank
165 works
₹17.57 Cr sanctioned
₹7.99 Cr spent (45%)
03
Rural Housing
6,004 works
₹17.05 Cr sanctioned
₹9.78 Cr spent (57%)
04
Farm Pond
406 works
₹10.58 Cr sanctioned
₹4.18 Cr spent (39%)
05
Construction of Check Dam/Stop Dam
127 works
₹9.54 Cr sanctioned
₹4.52 Cr spent (47%)
06
Construction of Well
318 works
₹7.26 Cr sanctioned
₹3.54 Cr spent (49%)
07
Land Development
171 works
₹6.33 Cr sanctioned
₹3.47 Cr spent (55%)
08
Construction of Road and Culvert
35 works
₹4.76 Cr sanctioned
₹3.91 Cr spent (82%)
09
Repair & maint of Pond/ Tank
74 works
₹4.67 Cr sanctioned
₹1.77 Cr spent (38%)
10
Construction of Percolation Tank
84 works
₹3.57 Cr sanctioned
₹1.87 Cr spent (52%)